Delhi-NCR Developers bat for exemption from the construction ban
12 Jan 2023
3 Min Read
CW Team
Developers of real estate have urged the central government to consider RERA-registered projects to be in the public interest and to permit the work to continue even if pollution levels rise. Developers met with Minister of Environment, Forest, and Climate Change Bhupender Yadav, who informed them that construction and demolition have already been prohibited for 29 days this winter.
鈥淧ractically, once construction activity ceases, it takes more than 15 to 30 days to resume full-fledged operations; consequently, in a nutshell, it would not be incorrect to note that construction is prohibited for two and a half months. Experts estimate that a "construction ban" lasting one week has an impact on a "construction site" for more than a month, resulting in a significant loss for real estate firms, laborers, vendors, ancillary businesses, and government revenue, according to Manoj Gaur, President of CREDAI-NCR.
According to developers, the laborers employed on construction sites will be directly affected by this ban for the first time. The workers come to Delhi NCR from a variety of states. When they become unemployed as a result of the frequent ban on construction in Delhi NCR, they return to their respective states, which, in addition to causing them to become unemployed, delays the process of handing over the apartment to affluent homebuyers.
We have pleaded with the minister to permit activities that do not pollute. Additionally, the sectors suffer from frequent bans, and the government ought to announce in advance that no construction will be permitted in the NCR during this time of year, according to Harsh V Bansal, convenor of the CII Delhi Sub-committee on Real Estate, Urban Development, and Infrastructure.
According to the industry body, vendors and ancillary businesses that sell construction materials like steel, paint, plywood, and cement can't sell during the ban, which costs the government GST.
Developers do not even get the "time extension" benefit against "time-loss," delay in construction, and delayed possession to homebuyers, which even attracts the "delay penalty" at the time of possession because the ban on construction activities due to pollution is not recognised by RERA, the development authorities, or the town planning department.
The issue and impact of an ad hoc blanket ban on all construction activities are distinct. Lalit Aggarwal, Co-founder and Vice Chairman of Signature Global, stated, "It not only adds to the cost of construction but also delays the project."
According to Aggarwal, "Given that, most projects have a completion deadline as per RERA compliance, even for affordable housing projects, where there is a statutory timeline of four years to complete the project, such bans every year cumulatively delay the project significantly."
According to CREDAI, RERA-registered projects shall be considered a public interest project because they strictly adhere to government guidelines to minimise pollution and involve the general public's interest.
Developers of real estate have urged the central government to consider RERA-registered projects to be in the public interest and to permit the work to continue even if pollution levels rise. Developers met with Minister of Environment, Forest, and Climate Change Bhupender Yadav, who informed them that construction and demolition have already been prohibited for 29 days this winter.鈥淧ractically, once construction activity ceases, it takes more than 15 to 30 days to resume full-fledged operations; consequently, in a nutshell, it would not be incorrect to note that construction is prohibited for two and a half months. Experts estimate that a construction ban lasting one week has an impact on a construction site for more than a month, resulting in a significant loss for real estate firms, laborers, vendors, ancillary businesses, and government revenue, according to Manoj Gaur, President of CREDAI-NCR.According to developers, the laborers employed on construction sites will be directly affected by this ban for the first time. The workers come to Delhi NCR from a variety of states. When they become unemployed as a result of the frequent ban on construction in Delhi NCR, they return to their respective states, which, in addition to causing them to become unemployed, delays the process of handing over the apartment to affluent homebuyers.We have pleaded with the minister to permit activities that do not pollute. Additionally, the sectors suffer from frequent bans, and the government ought to announce in advance that no construction will be permitted in the NCR during this time of year, according to Harsh V Bansal, convenor of the CII Delhi Sub-committee on Real Estate, Urban Development, and Infrastructure.According to the industry body, vendors and ancillary businesses that sell construction materials like steel, paint, plywood, and cement can't sell during the ban, which costs the government GST.Developers do not even get the time extension benefit against time-loss, delay in construction, and delayed possession to homebuyers, which even attracts the delay penalty at the time of possession because the ban on construction activities due to pollution is not recognised by RERA, the development authorities, or the town planning department.The issue and impact of an ad hoc blanket ban on all construction activities are distinct. Lalit Aggarwal, Co-founder and Vice Chairman of Signature Global, stated, It not only adds to the cost of construction but also delays the project.According to Aggarwal, Given that, most projects have a completion deadline as per RERA compliance, even for affordable housing projects, where there is a statutory timeline of four years to complete the project, such bans every year cumulatively delay the project significantly.According to CREDAI, RERA-registered projects shall be considered a public interest project because they strictly adhere to government guidelines to minimise pollution and involve the general public's interest.
Next Story
ClickPost Launches Atlas to Benchmark E-commerce Logistics
ClickPost, a leading logistics intelligence platform, has launched Atlas, a subscription-based benchmarking tool designed to transform how e-commerce brands strategise logistics. Powered by ClickPost鈥檚 proprietary network, which processes over 50 million shipments each month, Atlas enables brands to benchmark key operational metrics in real time against industry peers and standards.Unlike traditional dashboards, Atlas delivers comparative insights鈥攆rom fulfilment speeds, RTO rates and average order values to city-level delivery times and sales data鈥攁llowing brands to identify operational..
Next Story
Kalyani Launches Two New LivingTree Towers in Bengaluru
Bengaluru-based Kalyani Developers has announced the launch of Towers 3 and 4 at its flagship residential project, Kalyani LivingTree, located in KIADB Aerospace Park. The expansion adds 525 premium 3BHK apartments, ranging from 1300 to 1600 sq ft, and over 7.5 lakh sq ft of built-up area. Prices start from Rs 1.2 crore.These towers, the most exclusive in Phase 1, offer uninterrupted pool and landscape views, and access to over 60 lifestyle amenities, two clubhouses totalling 1 lakh sq ft, and more than 80 per cent open space.LivingTree spans 25 acres and will comprise ten towers of 23鈥�24 fl..
Next Story
Blue Water Logistics IPO opens May 27
Hyderabad-based Blue Water Logistics is launching its Rs 40.5 crore IPO on May 27, 2025, which will remain open for subscription until May 29. The price band has been set at Rs 132 to Rs 135 per share, with a lot size of 1,000 shares. This is a book-built issue entirely comprising a fresh issue of 30 lakh equity shares. The IPO will be listed on the NSE Emerge platform.Smart Horizon Capital Advisors is the sole book-running lead manager, while Maashitla Securities will act as the registrar. The anchor book will open on May 26, 2025. The IPO allocates 8,35,000 shares to anchor investors, 1,56,0..