Around 425 infra projects note cost overruns worth Rs 4.83 lakh cr
ECONOMY & POLICY

Around 425 infra projects note cost overruns worth Rs 4.83 lakh cr

According to a report, around 425 infrastructure projects, each entailing a Rs 150 crore or more investment, have been hit by cost overruns of over Rs 4.83 lakh crore.

According to the Ministry of Statistics and Programme Implementation, which monitors infrastructure projects of Rs 150 crore and above, out of 1,579 projects, 425 projects declared cost overruns, and around 664 projects were delayed.

The ministry's latest report for March 2022 said, the total original cost of execution of the 1,579 projects was Rs 21,95,196.72 crore, and their expected completion cost is likely to be Rs 26,78,365.62 crore, which reflects total cost overruns of Rs 4,83,168.90 crore.

According to the report, the cost incurred on these projects till March 2022 stood at Rs 13,88,760.73 crore, which is 51.85 % of the expected cost of the projects.

However, the number of delayed projects is reduced to 561 if the delay is estimated based on the latest completion schedule.

Further, for 606 projects, neither the year of commissioning nor the tentative gestation period has been notified.

Out of the 664 delayed projects, 124 have been delayed for 13-24 months, 331 projects for 25-60 months, 94 for 1-12 months, 115 projects for 61 months, and more.

In these 664 delayed projects, the average time overrun was 42.41 months.

Reasons for time overruns as informed by various project executing agencies include delay in land acquisition, lack of infrastructure support and linkages, and delay in obtaining forest and environment clearances.

Delay in tendering, ordering, and equipment supply, delay in tie-up for project financing, change in scope, delay in finalisation of detailed engineering, and law and order problems are among the other reasons.

The report also mentioned state-wise lockdowns due to Covid-19 as a reason for the delay in execution of these projects.

It has also been observed that project agencies are not reporting revised cost estimations and commissioning schedules for many projects, which indicates that time and cost overrun figures are under-reported.


Also read: 443 infra projects hits cost overruns of Rs 4.45 lakh crore: Report

According to a report, around 425 infrastructure projects, each entailing a Rs 150 crore or more investment, have been hit by cost overruns of over Rs 4.83 lakh crore. According to the Ministry of Statistics and Programme Implementation, which monitors infrastructure projects of Rs 150 crore and above, out of 1,579 projects, 425 projects declared cost overruns, and around 664 projects were delayed. The ministry's latest report for March 2022 said, the total original cost of execution of the 1,579 projects was Rs 21,95,196.72 crore, and their expected completion cost is likely to be Rs 26,78,365.62 crore, which reflects total cost overruns of Rs 4,83,168.90 crore. According to the report, the cost incurred on these projects till March 2022 stood at Rs 13,88,760.73 crore, which is 51.85 % of the expected cost of the projects. However, the number of delayed projects is reduced to 561 if the delay is estimated based on the latest completion schedule. Further, for 606 projects, neither the year of commissioning nor the tentative gestation period has been notified. Out of the 664 delayed projects, 124 have been delayed for 13-24 months, 331 projects for 25-60 months, 94 for 1-12 months, 115 projects for 61 months, and more. In these 664 delayed projects, the average time overrun was 42.41 months. Reasons for time overruns as informed by various project executing agencies include delay in land acquisition, lack of infrastructure support and linkages, and delay in obtaining forest and environment clearances. Delay in tendering, ordering, and equipment supply, delay in tie-up for project financing, change in scope, delay in finalisation of detailed engineering, and law and order problems are among the other reasons. The report also mentioned state-wise lockdowns due to Covid-19 as a reason for the delay in execution of these projects. It has also been observed that project agencies are not reporting revised cost estimations and commissioning schedules for many projects, which indicates that time and cost overrun figures are under-reported. Image Source Also read: 443 infra projects hits cost overruns of Rs 4.45 lakh crore: Report

Next Story
Resources

Blum India brings Design Reverie to Hyderabad

Blum India hosted the Hyderabad edition of its signature event, Design Reverie, at the historic Taj Falaknuma Palace, making it a memorable evening for the city鈥檚 architecture and interior design community. As per news reports, the event combined modern design sensibilities with the grandeur of a palace setting and the spiritual charm of Sufi qawwali.This marked the third edition of the event, after previous gatherings in Delhi and Bangalore. In Hyderabad, the focus was on fostering relaxed yet meaningful dialogue among design professionals鈥攁way from the typical conference setup. The eveni..

Next Story
Resources

Hafele launches Platinum Studio in Nagpur

Hafele has expanded its franchise footprint in central India by opening a new Studio Partner Platinum showroom in Nagpur in collaboration with Onkar Furnitech. The studio was inaugurated by Nitin Gadkari, Minister of Road Transport and Highways, along with Padma Gupta, Director 鈥� HR & Customer Experience, Hafele South Asia.Located at Sarthak Plaza, South Ambazari Road, Laxmi Nagar, the showroom offers an immersive experience of Hafele鈥檚 wide-ranging interior and home solutions. Designed as a hands-on, real-life application space, the studio showcases Hafele鈥檚 full portfolio鈥攊ncludi..

Next Story
Resources

Truflo by Hindware wins GPTW honour again

Truflo by Hindware has been certified a Great Place to Work for the fourth consecutive year, reaffirming its commitment to a people-first culture. The certification was awarded by the Great Place to Work Institute following a rigorous evaluation of employee experience, leadership, culture, and HR practices.Known as India鈥檚 fastest-growing plastic pipes and fittings company, Truflo has focused on fostering an inclusive, innovative, and growth-driven work environment. The company prioritises employee well-being and professional development, creating a culture where people feel valued and empow..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement