443 infra projects hits cost overruns of Rs 4.45 lakh crore: Report
01 Mar 2022
2 Min Read
CW Team
A government report revealed that 443 infrastructure projects, with the cost of investment of over Rs 150 crore, have been hit by cost overruns totalling over Rs 4.45 lakh crore.
The Ministry of Statistics and Programme Implementation (MOSPI) monitors infrastructure projects of Rs 150 crore and above.
As per the report, till January 2022, expenditure incurred on these projects stood at Rs 13,16,293.63 crore or 48.76% of the estimated project cost.
From 1,671 such projects, 514 projects were delayed, and 443 reported cost overruns.
However, the number of delayed projects reduces to 381, based on the latest completion schedule.
Moreover, for 881 projects, neither the year of commissioning nor the tentative gestation period has been declared.
Out of the 514 delayed projects, 89 have a total delay of one to two months, 113 are delayed for 13-24 months, 204 for 25-60 months, and 108 projects have been delayed for over 61 months.
Overall estimated time overrun in these 514 delayed projects is 46.23 months.
Various agencies executing these projects notified reasons for time overrun, such as delay in land acquisition, delay in getting environment approvals, and shortage of infrastructure linkages and support.
Additional reasons include finalisation detail engineering delay, change in scope, law and order issues, and many other reasons.
According to the report, the state-wise lockdown due to the Covid-19 pandemic was one of the reasons for the delay.
It also mentioned that project agencies are not reporting revised cost estimates and schedule commissioning for various projects, which shows that time/cost overrun figures are under-reported.
Also read: 445 infra projects hits cost overrun of Rs 4.4 lakh crore
A government report revealed that 443 infrastructure projects, with the cost of investment of over Rs 150 crore, have been hit by cost overruns totalling over Rs 4.45 lakh crore.
The Ministry of Statistics and Programme Implementation (MOSPI) monitors infrastructure projects of Rs 150 crore and above.
As per the report, till January 2022, expenditure incurred on these projects stood at Rs 13,16,293.63 crore or 48.76% of the estimated project cost.
From 1,671 such projects, 514 projects were delayed, and 443 reported cost overruns.
However, the number of delayed projects reduces to 381, based on the latest completion schedule.
Moreover, for 881 projects, neither the year of commissioning nor the tentative gestation period has been declared.
Out of the 514 delayed projects, 89 have a total delay of one to two months, 113 are delayed for 13-24 months, 204 for 25-60 months, and 108 projects have been delayed for over 61 months.
Overall estimated time overrun in these 514 delayed projects is 46.23 months.
Various agencies executing these projects notified reasons for time overrun, such as delay in land acquisition, delay in getting environment approvals, and shortage of infrastructure linkages and support.
Additional reasons include finalisation detail engineering delay, change in scope, law and order issues, and many other reasons.
According to the report, the state-wise lockdown due to the Covid-19 pandemic was one of the reasons for the delay.
It also mentioned that project agencies are not reporting revised cost estimates and schedule commissioning for various projects, which shows that time/cost overrun figures are under-reported.
Image Source
Also read: 445 infra projects hits cost overrun of Rs 4.4 lakh crore
Next Story
Pune Railway Station Yard Remodelling Project Blueprint Finalised
The Railway authorities have finalised a comprehensive blueprint to remodel Pune Railway Station, which includes modernising the platforms and yard infrastructure. Tenders for various components of the project are expected to be issued soon, signalling that the yard remodelling initiative is finally progressing. The railway administration has indicated that the initial phase of the work is likely to commence between February and March of the coming year.This project has been under discussion for several years. Due to the large number of passengers arriving in Pune from other states鈥攑articula..
Next Story
Quadruple Rail Line Planned between Karjat and Panvel to Ease Traffic
In a major infrastructure move aimed at easing the burden on Mumbai鈥檚 overcrowded suburban railway system, the Mumbai Railway Vikas Corporation (MRVC) has proposed the construction of a quadruple railway line between Karjat and Panvel. The Rs 4.92 billion project is designed to significantly improve commuting experiences for thousands of daily passengers in Navi Mumbai and Raigad, two regions witnessing rapid urbanisation.At present, the Karjat-Panvel corridor operates with only a single pair of tracks鈥攐ne up and one down line鈥攔esulting in regular delays and severe overcrowding, particul..
Next Story
Southern Railway Speeds up Station Upgrades in Thiruvananthapuram
Southern Railway is advancing major development initiatives across key railway stations in Thiruvananthapuram, with completion targeted in the coming months.One of the major highlights is the transformation of Thiruvananthapuram North into a terminal station. This upgrade includes the construction of a new station building, installation of tactile paving for improved accessibility, two lifts, and platform shelters, all of which are expected to be completed by next month. Over the past three years, the station has already undergone significant improvements, including the raising of platforms, i..