Noida authority seals Grand Omaxe society over Rs 4.57 Bn dues
09 Sep 2024
2 Min Read
CW Team
The Noida Authority sealed the Grand Omaxe housing society, developed by Omaxe Buildhome in Sector 93B, on Friday due to the non-payment of dues amounting to Rs 4.57 billion. The developer had failed to deposit the required 25% of recalculated dues, approximately Rs 1.14 billion, following a reduction due to the Covid zero-period relief, even after opting for the relief package. The Authority announced that unsold flats and vacant land at three projects?Grand Omaxe (Omaxe Buildhome) in Sector 93B, Antriksh Golf View (Colourful Estate) in Sector 78, and Matrott (Skytech Constructions) in Sector 76?would be sealed after giving developers an extended period to reschedule their dues under the Uttar Pradesh government's relief package, based on recommendations from the Amitabh Kant committee.
It was highlighted that only 22 out of 57 defaulting projects in Noida had accepted the rehabilitation package, which provides a two-year zero-period relief from April 2020 to March 2022, exempting developers from interest and penalties caused by Covid-related lockdowns. However, 29 developers, with cumulative land dues of around Rs 69 billion, have not yet taken up the package, leaving over 12,700 flats pending.
As reported earlier by TOI, Noida Authority is also considering filing complaints with the police's Economic Offences Wing (EOW) against developers for diverting funds received from homebuyers elsewhere.
The Greater Noida Authority also held a meeting on Friday, urging developers to clear their dues and expedite the registration process. Additional CEO Saumya Srivastava noted that, of the 98 defaulter projects, 13 builders had cleared their outstanding amounts, while 58 had paid 25% of their dues.
Srivastava added that a total of 71 builders had benefited from the policy, and permission had been granted for the registration of 9,558 flats in these 71 projects. During the meeting, builders were instructed to expedite the registration of remaining flats.
Builders have up to six months from the date of permission to complete the registration process without incurring a late fee. If they fail to deposit the 25% amount, their land allotments are at risk of being cancelled. Additionally, GNIDA plans to approach the EOW to request a forensic audit of defaulting projects.
The Noida Authority sealed the Grand Omaxe housing society, developed by Omaxe Buildhome in Sector 93B, on Friday due to the non-payment of dues amounting to Rs 4.57 billion. The developer had failed to deposit the required 25% of recalculated dues, approximately Rs 1.14 billion, following a reduction due to the Covid zero-period relief, even after opting for the relief package. The Authority announced that unsold flats and vacant land at three projects?Grand Omaxe (Omaxe Buildhome) in Sector 93B, Antriksh Golf View (Colourful Estate) in Sector 78, and Matrott (Skytech Constructions) in Sector 76?would be sealed after giving developers an extended period to reschedule their dues under the Uttar Pradesh government's relief package, based on recommendations from the Amitabh Kant committee.
It was highlighted that only 22 out of 57 defaulting projects in Noida had accepted the rehabilitation package, which provides a two-year zero-period relief from April 2020 to March 2022, exempting developers from interest and penalties caused by Covid-related lockdowns. However, 29 developers, with cumulative land dues of around Rs 69 billion, have not yet taken up the package, leaving over 12,700 flats pending.
As reported earlier by TOI, Noida Authority is also considering filing complaints with the police's Economic Offences Wing (EOW) against developers for diverting funds received from homebuyers elsewhere.
The Greater Noida Authority also held a meeting on Friday, urging developers to clear their dues and expedite the registration process. Additional CEO Saumya Srivastava noted that, of the 98 defaulter projects, 13 builders had cleared their outstanding amounts, while 58 had paid 25% of their dues.
Srivastava added that a total of 71 builders had benefited from the policy, and permission had been granted for the registration of 9,558 flats in these 71 projects. During the meeting, builders were instructed to expedite the registration of remaining flats.
Builders have up to six months from the date of permission to complete the registration process without incurring a late fee. If they fail to deposit the 25% amount, their land allotments are at risk of being cancelled. Additionally, GNIDA plans to approach the EOW to request a forensic audit of defaulting projects.
Next Story
Mumbai-Ahmedabad Bullet Train Set to Launch by 2028
India’s first bullet train is set to revolutionize high-speed travel along the western corridor, with the Mumbai-Ahmedabad high-speed rail project aiming for a 2028 launch. This announcement marks a major milestone in India’s infrastructure goals, as it promises to reduce travel time between the two economic hubs from eight hours to just three.Spanning a planned 508-kilometre stretch, the corridor stands as a flagship example of Indo-Japanese collaboration in technology and engineering. Once operational, the train is expected to transform intercity mobility and place India among the select..
Next Story
Mumbai-Gandhinagar Train Service Enhances Passenger Capacity
The Mumbai Central–Gandhinagar Capital Vande Bharat Express has increased its passenger capacity by adding four additional AC chair car coaches to meet the growing commuter demand on one of India’s busiest business corridors. This upgrade, effective from 11 May, raised the train’s seating capacity from 1,128 to 1,440 passengers, allowing it to serve 936 more passengers daily in both directions. The increase was described as a practical measure to accommodate the surging demand on the busy Mumbai–Ahmedabad–Gandhinagar route, which regularly operates at over 150 percent seat occupancy...
Next Story
Delhi Plans 12 Sewage Plants to Clean Najafgarh Drain Efficiently
Delhi’s ambitious plan to improve the water quality of the Yamuna River has gained significant momentum as the Delhi Jal Board (DJB) has begun work on 12 new sewage treatment plants (STPs) aimed at reducing the volume of untreated sewage being discharged from the Najafgarh Drain.This initiative forms part of the ongoing efforts to clean the Yamuna and restore the river’s health, which has long been a critical environmental issue for the national capital. Given the alarming pollution levels in the Yamuna, experts and officials consider this project a vital step toward addressing the persist..