Conquering challenges in the construction of Medigadda Barrage of KLIS
ROADS & HIGHWAYS

Conquering challenges in the construction of Medigadda Barrage of KLIS

The Kaleshwaram Lift Irrigation Scheme (KLIS), one of the world鈥檚 largest irrigation projects, now operational, aims to irrigate 18.25 lakh acre in 13 districts and stabilise another 18.75 lakh acre in seven more districts of Telangana. In this article, we feature the challenges in constructing the Medigadda Barrage 鈥� the largest barrage of KLIS, constructed by Larsen & Toubro (L&T).

  • MV Ramakrishna Raju, Project Director, L&T, shares the major challenges involved in constructing this barrage and measures taken to overcome them:
  • 18.5 lakh cu m concreting in a stringent timeline of 18 months: This project required 1,850,000 cum of concrete in just 18 months, translating into an asking rate of 5,000 cum per day during peak months. Eight batching plants and 100+transit mixers making approximately 1,000 trips a day fed13 boom placers in different locations spread across 3 sq km to build 13-15 different structures across the site.
  • Meeting a massive requirement of aggregates, 20 lakh mt in 18 months: With an average daily requirement of 5,500 mt of aggregates, of different sizes varying from 10mm to 40mm according to the pour plan and grade of concrete, procurement, transportation and just-in-time delivery were critical considerations to meet targets. To meet the threat of rising water levels of the Godavari during the monsoons: Coffer dams, specially designed by experts, were constructed, reinforced with sheet piles to withstand a staggering discharge of 9 lakh cu m per second.
  • Mobilising a huge workforce: The manpower requirement of 5,500 was across various categories like fitters, carpenters, welders, gas-cutters, drivers, plumbers, operators, fabricators, supervisors, foremen, etc. Mobilising and retaining such large numbers of skilled workmen, required a high level of functionality and strong administration. They were provided excellent accommodation, canteen and drinking water facilities with RO plant, refreshed with chilled buttermilk and oral dehydration salts during the summer when temperatures reached 45*C. The waste management for the entire workforce was routed through waste treatment plants of various capacities.

Consider this: This landmark project achieved 13.9 million safe man-hours. Another reason to label this endeavour a true marvel!

The Kaleshwaram Lift Irrigation Scheme (KLIS), one of the world鈥檚 largest irrigation projects, now operational, aims to irrigate 18.25 lakh acre in 13 districts and stabilise another 18.75 lakh acre in seven more districts of Telangana. In this article, we feature the challenges in constructing the Medigadda Barrage 鈥� the largest barrage of KLIS, constructed by Larsen & Toubro (L&T). MV Ramakrishna Raju, Project Director, L&T, shares the major challenges involved in constructing this barrage and measures taken to overcome them: 18.5 lakh cu m concreting in a stringent timeline of 18 months: This project required 1,850,000 cum of concrete in just 18 months, translating into an asking rate of 5,000 cum per day during peak months. Eight batching plants and 100+transit mixers making approximately 1,000 trips a day fed13 boom placers in different locations spread across 3 sq km to build 13-15 different structures across the site. Meeting a massive requirement of aggregates, 20 lakh mt in 18 months: With an average daily requirement of 5,500 mt of aggregates, of different sizes varying from 10mm to 40mm according to the pour plan and grade of concrete, procurement, transportation and just-in-time delivery were critical considerations to meet targets. To meet the threat of rising water levels of the Godavari during the monsoons: Coffer dams, specially designed by experts, were constructed, reinforced with sheet piles to withstand a staggering discharge of 9 lakh cu m per second. Mobilising a huge workforce: The manpower requirement of 5,500 was across various categories like fitters, carpenters, welders, gas-cutters, drivers, plumbers, operators, fabricators, supervisors, foremen, etc. Mobilising and retaining such large numbers of skilled workmen, required a high level of functionality and strong administration. They were provided excellent accommodation, canteen and drinking water facilities with RO plant, refreshed with chilled buttermilk and oral dehydration salts during the summer when temperatures reached 45*C. The waste management for the entire workforce was routed through waste treatment plants of various capacities. Consider this: This landmark project achieved 13.9 million safe man-hours. Another reason to label this endeavour a true marvel!

Next Story
Infrastructure Urban

CRCL, IIT Delhi Sign MoU to Boost Science and Ease of Business

The Central Revenues Control Laboratory (CRCL), Central Board of Indirect Taxes and Customs (CBIC), Department of Revenue, Ministry of Finance, and the Indian Institute of Technology (IIT) Delhi signed a Memorandum of Understanding (MoU) toward trade facilitation and improving the ease of doing business. This MoU collaboration aims to foster R&D, innovation, and scientific excellence at CRCL, bolstering trade facilitation and regulatory efficiency.The MoU was signed by Prof. Rangan Banerjee, Director, IIT Delhi, and Shri V. Suresh, Director, CRCL, in presence of Shri Surjit Bhujabal, Speci..

Next Story
Infrastructure Urban

CAQM Sub-Committee Activates 27-Point Plan to Improve NCR Air Quality

The daily average AQI of Delhi has been hovering marginally above 200 threshold with forecast of slight improvement since last two days. Today, Delhi鈥檚 daily average Air Quality Index (AQI) clocked 213 (鈥楶oor鈥� category), as per the daily AQI Bulletin provided by the Central Pollution Control Board (CPCB), owing to variable winds. In wake of the average/ overall air quality of Delhi recording 鈥楶oor鈥� air quality category ranging between 201-300, the CAQM Sub-Committee on GRAP met today to take stock of the current air quality scenario of Delhi-NCR. While comprehensively reviewing the a..

Next Story
Infrastructure Urban

DoT Launches Financial Fraud Risk Indicator to Boost Cybersecurity

In a major step towards combating cyber fraud and financial crime, the Department of Telecommunications (DoT) has announced sharing of 鈥淔inancial Fraud Risk Indicator (FRI)鈥� with stakeholders- an output from a multi- dimensional analytical tool developed as part of the Digital Intelligence Platform (DIP) to empower financial institutions with advance actionable intelligence for cyber fraud prevention. This will enhance cyber protection and validation checks in case of mobile numbers flagged with this tool when digital payment is proposed to be made to such numbers.What is the 鈥淔inancial ..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement