Bengaluru’s Major Arterial Road Nears Completion
19 Feb 2025
2 Min Read
CW Team
The much-anticipated Major Arterial Road (MAR) project in Bengaluru is nearing completion, promising to transform connectivity between the city's southern and western regions. Spanning 10.8 kilometers, the corridor will reduce travel time from 1.5 hours to just 10 minutes, offering a crucial alternative to the tolled NICE Road.
The project, initially budgeted at Rs 4.65 billion ($56 million), has escalated to Rs 5.85 billion ($70 million) due to delays and rising costs. The Bangalore Development Authority (BDA) has secured 321 acres for the road, which runs from Challaghatta on Mysuru Road to Kadabagere Cross on Magadi Road. It passes through key areas like Kambipura, K Krishna Sagara, and Kommaghatta, integrating urban and rural sectors while easing congestion for thousands of daily commuters.
Delays and Roadblocks
Launched in 2011, the MAR project faced multiple setbacks, with tenders only issued in 2017 and construction beginning a year later. Originally slated for completion in August 2019, progress stalled due to pending approvals from the forest department and the delayed construction of a railway underpass near the Challaghatta Metro depot.
Despite these hurdles, BDA officials are optimistic, stating that all remaining issues are being resolved and the road should be operational within two months. The long-awaited project underscores concerns about Bengaluru’s slow infrastructure execution and the need for faster urban development strategies.
A Greener Future for Bengaluru
Beyond connectivity, the MAR project aligns with sustainable urban planning. By reducing reliance on the tolled NICE Road and cutting down fuel consumption, it is expected to lower carbon emissions in one of India’s most congested cities. The improved infrastructure could also boost public transport ridership, supporting a shift towards eco-friendly mobility solutions.
As Bengaluru continues its rapid expansion, the MAR project serves as a model for integrating infrastructure with sustainability, ensuring that future urban development balances efficiency, environmental impact, and civic progress.
The much-anticipated Major Arterial Road (MAR) project in Bengaluru is nearing completion, promising to transform connectivity between the city's southern and western regions. Spanning 10.8 kilometers, the corridor will reduce travel time from 1.5 hours to just 10 minutes, offering a crucial alternative to the tolled NICE Road.
The project, initially budgeted at Rs 4.65 billion ($56 million), has escalated to Rs 5.85 billion ($70 million) due to delays and rising costs. The Bangalore Development Authority (BDA) has secured 321 acres for the road, which runs from Challaghatta on Mysuru Road to Kadabagere Cross on Magadi Road. It passes through key areas like Kambipura, K Krishna Sagara, and Kommaghatta, integrating urban and rural sectors while easing congestion for thousands of daily commuters.
Delays and Roadblocks
Launched in 2011, the MAR project faced multiple setbacks, with tenders only issued in 2017 and construction beginning a year later. Originally slated for completion in August 2019, progress stalled due to pending approvals from the forest department and the delayed construction of a railway underpass near the Challaghatta Metro depot.
Despite these hurdles, BDA officials are optimistic, stating that all remaining issues are being resolved and the road should be operational within two months. The long-awaited project underscores concerns about Bengaluru’s slow infrastructure execution and the need for faster urban development strategies.
A Greener Future for Bengaluru
Beyond connectivity, the MAR project aligns with sustainable urban planning. By reducing reliance on the tolled NICE Road and cutting down fuel consumption, it is expected to lower carbon emissions in one of India’s most congested cities. The improved infrastructure could also boost public transport ridership, supporting a shift towards eco-friendly mobility solutions.
As Bengaluru continues its rapid expansion, the MAR project serves as a model for integrating infrastructure with sustainability, ensuring that future urban development balances efficiency, environmental impact, and civic progress.
Next Story
ClickPost Launches Atlas to Benchmark E-commerce Logistics
ClickPost, a leading logistics intelligence platform, has launched Atlas, a subscription-based benchmarking tool designed to transform how e-commerce brands strategise logistics. Powered by ClickPost’s proprietary network, which processes over 50 million shipments each month, Atlas enables brands to benchmark key operational metrics in real time against industry peers and standards.Unlike traditional dashboards, Atlas delivers comparative insights—from fulfilment speeds, RTO rates and average order values to city-level delivery times and sales data—allowing brands to identify operational..
Next Story
Kalyani Launches Two New LivingTree Towers in Bengaluru
Bengaluru-based Kalyani Developers has announced the launch of Towers 3 and 4 at its flagship residential project, Kalyani LivingTree, located in KIADB Aerospace Park. The expansion adds 525 premium 3BHK apartments, ranging from 1300 to 1600 sq ft, and over 7.5 lakh sq ft of built-up area. Prices start from Rs 1.2 crore.These towers, the most exclusive in Phase 1, offer uninterrupted pool and landscape views, and access to over 60 lifestyle amenities, two clubhouses totalling 1 lakh sq ft, and more than 80 per cent open space.LivingTree spans 25 acres and will comprise ten towers of 23�24 fl..
Next Story
Blue Water Logistics IPO opens May 27
Hyderabad-based Blue Water Logistics is launching its Rs 40.5 crore IPO on May 27, 2025, which will remain open for subscription until May 29. The price band has been set at Rs 132 to Rs 135 per share, with a lot size of 1,000 shares. This is a book-built issue entirely comprising a fresh issue of 30 lakh equity shares. The IPO will be listed on the NSE Emerge platform.Smart Horizon Capital Advisors is the sole book-running lead manager, while Maashitla Securities will act as the registrar. The anchor book will open on May 26, 2025. The IPO allocates 8,35,000 shares to anchor investors, 1,56,0..