Bengaluru's Major Arterial Road to Link South and West in 2 Months
19 Feb 2025
2 Min Read
CW Team
The 10.8 km toll-free Major Arterial Road (MAR), designed to enhance connectivity between south and west Bengaluru, is expected to be completed in the coming months. The 10-lane road extends from Challaghatta, near the Namma Metro depot on Mysuru Road, to Kadabagere Cross on Magadi Road. Running parallel to the tolled NICE corridor, it is positioned approximately 2 km away and is anticipated to significantly reduce travel time between these regions from 1.5 hours to just 10 minutes.
Developed by the Bangalore Development Authority (BDA), the project initially had an estimated cost of Rs 4.65 billion, which has now escalated to Rs 5.85 billion. The road passes through several villages, including Kambipura, K Krishna Sagara, Bheemanakuppe, Kommaghatta, Kenchanapura, and Sulikere. One of its key benefits is providing direct access to BDA鈥檚 Nadaprabhu Kempegowda Layout (NPKL), improving connectivity for residents in the area.
The project has encountered multiple challenges, particularly in land acquisition and environmental clearances. The acquisition of 321.1 acre faced delays, and ongoing discussions with the forest department are holding up the approval for diverting 2 acres of land within the Sulikere reserve forest. Additionally, a railway underpass along the route is under construction, while 300 meters of the road near Mysuru Road remain incomplete, awaiting the finalisation of the Challaghatta Metro depot work.
The land acquisition process began with notification on July 27, 2011. However, tenders were issued only in September 2017, and construction commenced in 2018. The original deadline for completion was August 2019, but due to various setbacks, the project has been delayed. Despite these challenges, authorities expect the road to be operational soon.
News source: Hans India
The 10.8 km toll-free Major Arterial Road (MAR), designed to enhance connectivity between south and west Bengaluru, is expected to be completed in the coming months. The 10-lane road extends from Challaghatta, near the Namma Metro depot on Mysuru Road, to Kadabagere Cross on Magadi Road. Running parallel to the tolled NICE corridor, it is positioned approximately 2 km away and is anticipated to significantly reduce travel time between these regions from 1.5 hours to just 10 minutes.
Developed by the Bangalore Development Authority (BDA), the project initially had an estimated cost of Rs 4.65 billion, which has now escalated to Rs 5.85 billion. The road passes through several villages, including Kambipura, K Krishna Sagara, Bheemanakuppe, Kommaghatta, Kenchanapura, and Sulikere. One of its key benefits is providing direct access to BDA鈥檚 Nadaprabhu Kempegowda Layout (NPKL), improving connectivity for residents in the area.
The project has encountered multiple challenges, particularly in land acquisition and environmental clearances. The acquisition of 321.1 acre faced delays, and ongoing discussions with the forest department are holding up the approval for diverting 2 acres of land within the Sulikere reserve forest. Additionally, a railway underpass along the route is under construction, while 300 meters of the road near Mysuru Road remain incomplete, awaiting the finalisation of the Challaghatta Metro depot work.
The land acquisition process began with notification on July 27, 2011. However, tenders were issued only in September 2017, and construction commenced in 2018. The original deadline for completion was August 2019, but due to various setbacks, the project has been delayed. Despite these challenges, authorities expect the road to be operational soon.
News source: Hans India
Next Story
Mumbai-Ahmedabad Bullet Train Set to Launch by 2028
India鈥檚 first bullet train is set to revolutionize high-speed travel along the western corridor, with the Mumbai-Ahmedabad high-speed rail project aiming for a 2028 launch. This announcement marks a major milestone in India鈥檚 infrastructure goals, as it promises to reduce travel time between the two economic hubs from eight hours to just three.Spanning a planned 508-kilometre stretch, the corridor stands as a flagship example of Indo-Japanese collaboration in technology and engineering. Once operational, the train is expected to transform intercity mobility and place India among the select..
Next Story
Mumbai-Gandhinagar Train Service Enhances Passenger Capacity
The Mumbai Central鈥揋andhinagar Capital Vande Bharat Express has increased its passenger capacity by adding four additional AC chair car coaches to meet the growing commuter demand on one of India鈥檚 busiest business corridors. This upgrade, effective from 11 May, raised the train鈥檚 seating capacity from 1,128 to 1,440 passengers, allowing it to serve 936 more passengers daily in both directions. The increase was described as a practical measure to accommodate the surging demand on the busy Mumbai鈥揂hmedabad鈥揋andhinagar route, which regularly operates at over 150 percent seat occupancy...
Next Story
Delhi Plans 12 Sewage Plants to Clean Najafgarh Drain Efficiently
Delhi鈥檚 ambitious plan to improve the water quality of the Yamuna River has gained significant momentum as the Delhi Jal Board (DJB) has begun work on 12 new sewage treatment plants (STPs) aimed at reducing the volume of untreated sewage being discharged from the Najafgarh Drain.This initiative forms part of the ongoing efforts to clean the Yamuna and restore the river鈥檚 health, which has long been a critical environmental issue for the national capital. Given the alarming pollution levels in the Yamuna, experts and officials consider this project a vital step toward addressing the persist..