Chenab bridge arch to be completed today
05 Apr 2021
3 Min Read
Editorial Team
The nearly 0.5 km long arch of the world's tallest railway bridge—the Chenab bridge in the Kauri area of Jammu and Kashmir━is all set to be completed today.
The 5.3 m last piece of metal will be fitted at the highest point today and join the two arms of the arch that currently stretch towards each other from both the river banks. This will complete the arch's shape that will then loom 359 m above the Chenab river.
The arch is the most difficult part of the Rs 1,400 crore Chenab bridge that will complete the 111 km long stretch connecting Katra with Banihal. It will symbolise the Kashmir rail link to be ready for at least a century.
Currently, the Kashmir link means a 25 km stretch from Udhampur to Katra, an 18 km stretch from Banihal to Qazigund in the Valley and thereafter the 118 km Qazigund to Baramulla line. All these lines have been operational for years. The only missing piece in the link is the Katra-Banihal stretch, and the bridge over Chenab was the main engineering hurdle holding up the progress all these years.
The cable crane that will complete the arch measures around 900 m and is said to be the longest in the world, made especially for this project. Over the last 2.5 years, engineers have been building the arch with the help of two mammoth cable cranes installed on both banks of the Chenab—the Kauri end and the Bakkal end.
A major challenge was that the 550 m arch, weighing 10,000 metric tonne, had to stand only with the support from the two embankments and without any intermediate pier since the river is 359 meters below and no pier could possibly come at a height like that.
From "support to support", the distance is 467 m. The whole bridge is going to weigh around 29,000 metric tonne. Engineers started work from both embankments simultaneously, starting with the installation of the cranes that would launch the arch.
Each specially designed cable crane, installed at the two banks by Afcons, are around a kilometre long. The two cranes have been working independently and also in synchrony, from each bank and joining pieces of the arch bit by bit.
For the wielding of the pieces, a national accredited welding lab cum workshop was erected on the construction site to speed up work—a first for a project in India. Steel pieces are cut with computerised machines and are then tested as per the standard before being approved for deployment.
Also read: World’s tallest railway bridge by Indian Railways
Also read: Railways completes arch bottom of tallest rail bridge
The nearly 0.5 km long arch of the world's tallest railway bridge—the Chenab bridge in the Kauri area of Jammu and Kashmir━is all set to be completed today.
The 5.3 m last piece of metal will be fitted at the highest point today and join the two arms of the arch that currently stretch towards each other from both the river banks. This will complete the arch's shape that will then loom 359 m above the Chenab river.
The arch is the most difficult part of the Rs 1,400 crore Chenab bridge that will complete the 111 km long stretch connecting Katra with Banihal. It will symbolise the Kashmir rail link to be ready for at least a century.
Currently, the Kashmir link means a 25 km stretch from Udhampur to Katra, an 18 km stretch from Banihal to Qazigund in the Valley and thereafter the 118 km Qazigund to Baramulla line. All these lines have been operational for years. The only missing piece in the link is the Katra-Banihal stretch, and the bridge over Chenab was the main engineering hurdle holding up the progress all these years.
The cable crane that will complete the arch measures around 900 m and is said to be the longest in the world, made especially for this project. Over the last 2.5 years, engineers have been building the arch with the help of two mammoth cable cranes installed on both banks of the Chenab—the Kauri end and the Bakkal end.
A major challenge was that the 550 m arch, weighing 10,000 metric tonne, had to stand only with the support from the two embankments and without any intermediate pier since the river is 359 meters below and no pier could possibly come at a height like that.
From support to support, the distance is 467 m. The whole bridge is going to weigh around 29,000 metric tonne. Engineers started work from both embankments simultaneously, starting with the installation of the cranes that would launch the arch.
Each specially designed cable crane, installed at the two banks by Afcons, are around a kilometre long. The two cranes have been working independently and also in synchrony, from each bank and joining pieces of the arch bit by bit.
For the wielding of the pieces, a national accredited welding lab cum workshop was erected on the construction site to speed up work—a first for a project in India. Steel pieces are cut with computerised machines and are then tested as per the standard before being approved for deployment.
Image Source
Also read: World’s tallest railway bridge by Indian Railways
Also read: Railways completes arch bottom of tallest rail bridge
Next Story
CRCL, IIT Delhi Sign MoU to Boost Science and Ease of Business
The Central Revenues Control Laboratory (CRCL), Central Board of Indirect Taxes and Customs (CBIC), Department of Revenue, Ministry of Finance, and the Indian Institute of Technology (IIT) Delhi signed a Memorandum of Understanding (MoU) toward trade facilitation and improving the ease of doing business. This MoU collaboration aims to foster R&D, innovation, and scientific excellence at CRCL, bolstering trade facilitation and regulatory efficiency.The MoU was signed by Prof. Rangan Banerjee, Director, IIT Delhi, and Shri V. Suresh, Director, CRCL, in presence of Shri Surjit Bhujabal, Speci..
Next Story
CAQM Sub-Committee Activates 27-Point Plan to Improve NCR Air Quality
The daily average AQI of Delhi has been hovering marginally above 200 threshold with forecast of slight improvement since last two days. Today, Delhi’s daily average Air Quality Index (AQI) clocked 213 (‘Poor� category), as per the daily AQI Bulletin provided by the Central Pollution Control Board (CPCB), owing to variable winds. In wake of the average/ overall air quality of Delhi recording ‘Poor� air quality category ranging between 201-300, the CAQM Sub-Committee on GRAP met today to take stock of the current air quality scenario of Delhi-NCR. While comprehensively reviewing the a..
Next Story
DoT Launches Financial Fraud Risk Indicator to Boost Cybersecurity
In a major step towards combating cyber fraud and financial crime, the Department of Telecommunications (DoT) has announced sharing of “Financial Fraud Risk Indicator (FRI)� with stakeholders- an output from a multi- dimensional analytical tool developed as part of the Digital Intelligence Platform (DIP) to empower financial institutions with advance actionable intelligence for cyber fraud prevention. This will enhance cyber protection and validation checks in case of mobile numbers flagged with this tool when digital payment is proposed to be made to such numbers.What is the “Financial ..