Mumbai suburban rail's longest tunnel completes on Panvel-Karjat line
11 Jun 2024
2 Min Read
CW Team
The Mumbai Railway Vikas Corporation (MRVC) announced a significant achievement with the breakthrough of the 2,625m Wavarle tunnel, marking it as the longest tunnel in the Mumbai suburban railway network. This tunnel forms part of the Panvel-Karjat railway project, which is under the Mumbai Urban Transport Project-3 (MUTP-3). Construction on this project commenced on February 22 of the previous year.
According to Sunil Udasi, the chief public relations officer of MRVC, the Panvel-Karjat railway project entails the construction of three tunnels totaling 3,164m. Breakthroughs for the Nadhamuni (219m) and Kirawali (320m) tunnels were also achieved. MRVC has completed 50% of the Rs 27.82-billion project and aims to open it by December 2025.
The Wavarle tunnel, constructed using the new Austrian tunnelling method, involves cyclic excavation followed by primary support and delayed secondary lining. The tunnel includes features such as a ballastless track, public refuge areas, a tunnel control system, lighting, firefighting, and ventilation systems meeting international standards. It measures 7.32m tall and 13.28m wide.
Excavation encountered significant challenges, including fractured rock masses with water seepage and minimal cover as low as 12m. Two water streams cross the tunnel alignment at the low cover zone. Despite these difficulties, an average excavation output of 175m per month was achieved through careful planning and daytime blasting, as night blasting is prohibited.
The new double-line corridor is expected to enhance connectivity by enabling local trains to operate between Mumbai and Karjat via Panvel, supplementing the existing line primarily used for goods trains and a few long-distance passenger services. It will also connect Navi Mumbai with Raigad district and serve as a catalyst for the development of Panvel, Karjat, and the proposed Navi Mumbai Airport Influence Notified Area.
The Mumbai Railway Vikas Corporation (MRVC) announced a significant achievement with the breakthrough of the 2,625m Wavarle tunnel, marking it as the longest tunnel in the Mumbai suburban railway network. This tunnel forms part of the Panvel-Karjat railway project, which is under the Mumbai Urban Transport Project-3 (MUTP-3). Construction on this project commenced on February 22 of the previous year.
According to Sunil Udasi, the chief public relations officer of MRVC, the Panvel-Karjat railway project entails the construction of three tunnels totaling 3,164m. Breakthroughs for the Nadhamuni (219m) and Kirawali (320m) tunnels were also achieved. MRVC has completed 50% of the Rs 27.82-billion project and aims to open it by December 2025.
The Wavarle tunnel, constructed using the new Austrian tunnelling method, involves cyclic excavation followed by primary support and delayed secondary lining. The tunnel includes features such as a ballastless track, public refuge areas, a tunnel control system, lighting, firefighting, and ventilation systems meeting international standards. It measures 7.32m tall and 13.28m wide.
Excavation encountered significant challenges, including fractured rock masses with water seepage and minimal cover as low as 12m. Two water streams cross the tunnel alignment at the low cover zone. Despite these difficulties, an average excavation output of 175m per month was achieved through careful planning and daytime blasting, as night blasting is prohibited.
The new double-line corridor is expected to enhance connectivity by enabling local trains to operate between Mumbai and Karjat via Panvel, supplementing the existing line primarily used for goods trains and a few long-distance passenger services. It will also connect Navi Mumbai with Raigad district and serve as a catalyst for the development of Panvel, Karjat, and the proposed Navi Mumbai Airport Influence Notified Area.
Next Story
3i Infotech Reports Rs 7.25 Bn Revenue for FY25
3i Infotech, a leading provider of digital transformation, technology services and technology solutions, announced its consolidated financial results for the fourth quarter and full year FY25, ended on March 31st, 2025. The company maintained its growth momentum, displaying consistent progress for the 3rd consecutive quarter.In Q4 FY25, 3i Infotech reported revenue of Rs 1.87 billion, reflecting steady performance compared to Rs 1.81 billion in Q3 FY25 and Rs 1.97 billion in Q4 FY24. The company delivered strong profitability improvements, with gross margin growing by 14.8 per cent Q-o-Q and 1..
Next Story
Emerald Finance Joins Baya PTE to Boost SME Bill Discounting
Emerald Finance is a dynamic company offering a spectrum of financial products and services including its flagship Earned Wage Access (EWA) in India, has entered into a strategic partnership with Singapore-based Baya PTE through its Indian subsidiary. This collaboration aims to strengthen bill discounting services for Small and Medium Enterprises (SMEs), enabling faster access to working capital and improved cash flow management.The initiative is designed to support SMEs that supply to large corporates such as JSW Steel, Delhivery, and PVR INOX, among others. By facilitating timely invoice dis..
Next Story
BLS E-Services Crosses Rs 5 Bn Revenue Mark in FY25
BLS E-Services, a technology-enabled digital service provider, announced its audited consolidated financial results for the quarter and full year period ended 31 March 2025.Speaking about the performance and recent updates, Shikhar Aggarwal, Chairman, BLS E- Services said, 鈥淲e are delighted to report a remarkable performance in FY25, as we achieved several milestones during the fiscal year. FY25 marked our highest-ever financial performance, as we surpassed Rs 5 billion milestone in Total Income during the year, which was reported at Rs 5.45 billion, a notable YoY growth of 76 per cent. The ..