Thane-Bhiwandi Metro Line-5: MMRDA Achieves Milestone
09 Oct 2024
2 Min Read
CW Team
The Mumbai Metropolitan Region Development Authority (MMRDA) has announced a significant milestone in the ongoing Metro Line-5 (Thane - Bhiwandi) project with the successful erection of two special spans -- 57.50m and 46.00m -- using high-capacity cranes (450T & 700T).
This complex operation, which required immense engineering expertise and precision, was especially challenging as it took place not only in the middle of a busy road, but also right above the Majiwada Flyover, in a densely populated residential area.
鈥淕iven the location, we had to take extensive precautions, ensuring that all safety regulations were strictly followed and that local rules were adhered to. Despite the added difficulty, the team executed the operation seamlessly in just five hours during the night, minimizing traffic disruption thanks to the approval and support of local authorities,鈥� MMRDA Metropolitan Commissioner Dr Sanjay Mukherjee said in a social media post.
鈥淔or the 57.50m span between Pier 10-11, tandem lifting of girders weighing 290 MT was carried out on Ghodbunder Road. Similarly, the 46.00m span on the Thane-Bhiwandi road was completed using a super-lift arrangement due to the 20m crane radius. This achievement underscores the team's technical competence and dedication to timely project completion, setting a benchmark for future phases. Traffic was restored promptly after the operations, and the local community was minimally impacted,鈥� Mukherjee added.
The Mumbai Metro Line 5 project is being carried out in two phases. Phase-I between Thane and Bhiwandi is 12.7 km in length with a total of six elevated metro stations.
鈥淎lmost 93% of the civil works for Phase I has been completed. While the track work and architectural finishes are in progress. The depot for Metro Line 5 is planned at Kasheli and contractor has started preliminary works at the depot. The sanctioned project completion cost for Metro Line 5 is Rs. 8,417 crore,鈥� a senior MMRDA official said adding, the process of appointing a general consultant for the Phase-2 between Bhiwandi and Kalyan is in progress while the appointment of the civil contractor for construction work of Phase-II is planned subsequently. The Metro Line 5 will provide inter-connectivity with the ongoing Metro Line 4 (Wadala-Kasarvadavli) and the proposed Metro Line 12 (Kalyan-Taloja), apart from the existing Central Railway suburban service.
The Mumbai Metropolitan Region Development Authority (MMRDA) has announced a significant milestone in the ongoing Metro Line-5 (Thane - Bhiwandi) project with the successful erection of two special spans -- 57.50m and 46.00m -- using high-capacity cranes (450T & 700T).
This complex operation, which required immense engineering expertise and precision, was especially challenging as it took place not only in the middle of a busy road, but also right above the Majiwada Flyover, in a densely populated residential area.
鈥淕iven the location, we had to take extensive precautions, ensuring that all safety regulations were strictly followed and that local rules were adhered to. Despite the added difficulty, the team executed the operation seamlessly in just five hours during the night, minimizing traffic disruption thanks to the approval and support of local authorities,鈥� MMRDA Metropolitan Commissioner Dr Sanjay Mukherjee said in a social media post.
鈥淔or the 57.50m span between Pier 10-11, tandem lifting of girders weighing 290 MT was carried out on Ghodbunder Road. Similarly, the 46.00m span on the Thane-Bhiwandi road was completed using a super-lift arrangement due to the 20m crane radius. This achievement underscores the team's technical competence and dedication to timely project completion, setting a benchmark for future phases. Traffic was restored promptly after the operations, and the local community was minimally impacted,鈥� Mukherjee added.
The Mumbai Metro Line 5 project is being carried out in two phases. Phase-I between Thane and Bhiwandi is 12.7 km in length with a total of six elevated metro stations. 鈥淎lmost 93% of the civil works for Phase I has been completed. While the track work and architectural finishes are in progress. The depot for Metro Line 5 is planned at Kasheli and contractor has started preliminary works at the depot. The sanctioned project completion cost for Metro Line 5 is Rs. 8,417 crore,鈥� a senior MMRDA official said adding, the process of appointing a general consultant for the Phase-2 between Bhiwandi and Kalyan is in progress while the appointment of the civil contractor for construction work of Phase-II is planned subsequently. The Metro Line 5 will provide inter-connectivity with the ongoing Metro Line 4 (Wadala-Kasarvadavli) and the proposed Metro Line 12 (Kalyan-Taloja), apart from the existing Central Railway suburban service.
Next Story
3i Infotech Reports Rs 7.25 Bn Revenue for FY25
3i Infotech, a leading provider of digital transformation, technology services and technology solutions, announced its consolidated financial results for the fourth quarter and full year FY25, ended on March 31st, 2025. The company maintained its growth momentum, displaying consistent progress for the 3rd consecutive quarter.In Q4 FY25, 3i Infotech reported revenue of Rs 1.87 billion, reflecting steady performance compared to Rs 1.81 billion in Q3 FY25 and Rs 1.97 billion in Q4 FY24. The company delivered strong profitability improvements, with gross margin growing by 14.8 per cent Q-o-Q and 1..
Next Story
Emerald Finance Joins Baya PTE to Boost SME Bill Discounting
Emerald Finance is a dynamic company offering a spectrum of financial products and services including its flagship Earned Wage Access (EWA) in India, has entered into a strategic partnership with Singapore-based Baya PTE through its Indian subsidiary. This collaboration aims to strengthen bill discounting services for Small and Medium Enterprises (SMEs), enabling faster access to working capital and improved cash flow management.The initiative is designed to support SMEs that supply to large corporates such as JSW Steel, Delhivery, and PVR INOX, among others. By facilitating timely invoice dis..
Next Story
BLS E-Services Crosses Rs 5 Bn Revenue Mark in FY25
BLS E-Services, a technology-enabled digital service provider, announced its audited consolidated financial results for the quarter and full year period ended 31 March 2025.Speaking about the performance and recent updates, Shikhar Aggarwal, Chairman, BLS E- Services said, 鈥淲e are delighted to report a remarkable performance in FY25, as we achieved several milestones during the fiscal year. FY25 marked our highest-ever financial performance, as we surpassed Rs 5 billion milestone in Total Income during the year, which was reported at Rs 5.45 billion, a notable YoY growth of 76 per cent. The ..