Nagpur Metro Phase 1 consisted of two corridors, North-South and East-West, with a total length of 41.7 km. Of this, 17.087 km (41 per cent of the viaduct) was awarded to Afcons in the Reach 2 (North-South corridor) and Reach 3 (East-West corridor) stretches. Afcons executed the Reach 2 package in the North-South corridor, which consists of a 5-km double-decker structure and 1.7-km metro viaduct structure that starts from Automotive Square on Kamptee Road and ends at Sitabuldi.

The double-decker flyover structure consists of two decks: flyover level and metro level. The decks are constructed with precast segments. The flyover level consists of two segments: spine and wings. The team adopted Value Stream Mapping (VSM) to improve the cycle time by ~50 per cent, from 28 days to 14 days. Some key interventions were:

  • Improvement in sequence of construction operations allowing for simultaneously launching wing segments and launcher (after erection of three cantilever arms)
  • Analysis of idle time to optimise use of trailers for transportation of both segments and wings
  • Simultaneous operations for wings alignment, shutter fixing and rebar fixing
  • Minimising time at site operations through use of boom placer instead of stationary pump and higher grade of concrete
  • Use of manlift for stressing to decouple working site and ground traffic.

Nagpur Metro Phase 1 consisted of two corridors, North-South and East-West, with a total length of 41.7 km. Of this, 17.087 km (41 per cent of the viaduct) was awarded to Afcons in the Reach 2 (North-South corridor) and Reach 3 (East-West corridor) stretches. Afcons executed the Reach 2 package in the North-South corridor, which consists of a 5-km double-decker structure and 1.7-km metro viaduct structure that starts from Automotive Square on Kamptee Road and ends at Sitabuldi. The double-decker flyover structure consists of two decks: flyover level and metro level. The decks are constructed with precast segments. The flyover level consists of two segments: spine and wings. The team adopted Value Stream Mapping (VSM) to improve the cycle time by ~50 per cent, from 28 days to 14 days. Some key interventions were: Improvement in sequence of construction operations allowing for simultaneously launching wing segments and launcher (after erection of three cantilever arms)Analysis of idle time to optimise use of trailers for transportation of both segments and wingsSimultaneous operations for wings alignment, shutter fixing and rebar fixingMinimising time at site operations through use of boom placer instead of stationary pump and higher grade of concreteUse of manlift for stressing to decouple working site and ground traffic.

Next Story
Infrastructure Urban

CRCL, IIT Delhi Sign MoU to Boost Science and Ease of Business

The Central Revenues Control Laboratory (CRCL), Central Board of Indirect Taxes and Customs (CBIC), Department of Revenue, Ministry of Finance, and the Indian Institute of Technology (IIT) Delhi signed a Memorandum of Understanding (MoU) toward trade facilitation and improving the ease of doing business. This MoU collaboration aims to foster R&D, innovation, and scientific excellence at CRCL, bolstering trade facilitation and regulatory efficiency.The MoU was signed by Prof. Rangan Banerjee, Director, IIT Delhi, and Shri V. Suresh, Director, CRCL, in presence of Shri Surjit Bhujabal, Speci..

Next Story
Infrastructure Urban

CAQM Sub-Committee Activates 27-Point Plan to Improve NCR Air Quality

The daily average AQI of Delhi has been hovering marginally above 200 threshold with forecast of slight improvement since last two days. Today, Delhi鈥檚 daily average Air Quality Index (AQI) clocked 213 (鈥楶oor鈥� category), as per the daily AQI Bulletin provided by the Central Pollution Control Board (CPCB), owing to variable winds. In wake of the average/ overall air quality of Delhi recording 鈥楶oor鈥� air quality category ranging between 201-300, the CAQM Sub-Committee on GRAP met today to take stock of the current air quality scenario of Delhi-NCR. While comprehensively reviewing the a..

Next Story
Infrastructure Urban

DoT Launches Financial Fraud Risk Indicator to Boost Cybersecurity

In a major step towards combating cyber fraud and financial crime, the Department of Telecommunications (DoT) has announced sharing of 鈥淔inancial Fraud Risk Indicator (FRI)鈥� with stakeholders- an output from a multi- dimensional analytical tool developed as part of the Digital Intelligence Platform (DIP) to empower financial institutions with advance actionable intelligence for cyber fraud prevention. This will enhance cyber protection and validation checks in case of mobile numbers flagged with this tool when digital payment is proposed to be made to such numbers.What is the 鈥淔inancial ..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement