Know about the technique that led to the fulfillment of India's first underwater Metro tunnel in Kolkata
WATER & WASTE

Know about the technique that led to the fulfillment of India's first underwater Metro tunnel in Kolkata

Here's the buzz: Afcons Infrastructure has achieved a landmark by successfully boring 2.9-km twin tunnels below river Hooghly in the East West Metro Project, in Kolkata! One of the company's biggest achievements in the area of underground metro infrastructure has been the successful completion of tunnelling for India's first underwater Metro project. The tunnelling was completed in just 67 days against the budgeted 127 days, which attests to the company's meticulous planning and efficient execution. These tunnels connect two of the world's busiest railway stations, Howrah and Sealdah. Once operational, the service will revolutionise travel in Kolkata, the first city in India to have an underground metro.

Taking stock
While tunnelling has been done under rivers across the world, and some projects have met with success, Afcons was faced with several challenges when it took up a project of this magnitude. Detailed investigations, case studies, planning, design considerations and logistic arrangements were carried out before the tunnel-boring machines (TBMs) could plunge below the river.

What made the East West Metro Project even tougher was the alignment. It passes through challenging topography, necessitating tunnelling in the vicinity or directly below dilapidated buildings, railway offices, a busy and packed railway yard, busy roads, bridges and flyovers and heritage monuments. The geology of Kolkata and Howrah is erratic, especially the topmost stratum, which is soft and weak, adding to the challenge.

Precise planning

The engineers focussed on selecting suitable designs and technologies for the successful delivery of the project. The designing of this project was entrusted to specialised world-class design companies such as Atkins, Systra and Tunnelconsult. Afcons chose Herrenkeneckht TBMs for this project, based on its track record in manufacturing machines tailor-made for specific project requirements. HK is also engaged in the maintenance of the two TBMs deployed for the Kolkata Metro project.

While Kolkata Metro Rail Corporation (KMRCL) carried out soil investigation work at the pre-tender stage for feasibility study, Afcons carried out soil investigation work near the entire tunnel alignment, deploying floating barges and pontoons in the river portion. The company also conducted extensive surveys of the buildings in proximity to the alignment before carrying out tunnelling.

Unique challenges
While executing this project, the tunnel crew faced the unique problem of the TBMs moving through soft clay strata at a lesser depth over structures that are almost a century old. Some of them are ravaged to the extent of being dilapidated. Apart from the main Colvin Court building, the TBMs passed below the quarters for service staff, which are in poor shape. These structures house high-ranking Railways officials. Another issue of concern was mining below Howrah Railway Yard, one of the busiest railway yards in the country with over 670 running trains and a footfall of 10.5 lakh daily.

Boring below these structures was a herculean task. Mining had to be done over 350 m below the yard for each tunnel. The TBMs had to negotiate a sharp curve of radius 228 m, plunging into a new geology (stiff clay) and passed by the Bankim Setu piers. There are only a few comparable examples of such a tight curve undertaken in India. One more curve of 226 m radius was achieved near Rajbhawan before Esplanade Station.

Obtaining CRS approvals for the project was another gigantic task, and this was achieved after satisfactory closure of all requirements. The procedure was hectic, but it helped gain several insights into project management during the tunnelling operation.

Key innovations
Afcons deployed a highly experienced tunnel crew on board, should an entry into the cutting chamber be required under high hyperbaric pressures. In the remote possibility of river water ingress, the TBMs could shut down like a submarine for safe evacuation. A project of this scale involves a number of innovations and the engineers improved upon numerous processes while planning the project. Owing to site constraints, the TBMs had to be driven through Howrah station in advance. This was a delicate operation, where they could encounter difficulty in crossing the diaphragm walls. Afcons designed a 'soft eye' of Styrofoam replacing M-40 concrete, which worked extremely well for this project. This is a first-of-its-kind attempted in India by in-house design engineers.

Relief measures
Special efforts were made to ensure that there was no loss of life and property during the TBM operations. More than five teams were deployed to carry out extensive repairs in all critical buildings. There was no compromise on safety, with adequate traffic diversions, restricted pedestrian movements and timely evacuations. About 300 people were relocated to hotels during tunnelling operation near their premises, and were brought back safely to their homes after the task was completed. This gesture won Afcons accolades from the public, government authorities, and others, and set new standards in project management.

Last-minute risks
This project has been a learning curve for Afcons. Underground tunnelling is in itself a challenging task, but underwater tunnelling is far more complex and risky. The chances of water ingress are high and so are the possibilities of geological surprises owing to the impact of tunnelling. Once the tunnelling began under the riverbed, the team ensured it did not stop under any circumstances. In underwater tunnelling, the bore had to be dug much deeper owing to the possibility of water inflow. This required a high level of detailing, precision and preparation. The meticulous planning bore fruit with the TBMs crossing the river seamlessly covering a distance of 11-12 m daily.

About the author: Virender Kaul is Project Manager of East West Metro Project, Kolkata.

Share your views on this article at [email protected]

Here's the buzz: Afcons Infrastructure has achieved a landmark by successfully boring 2.9-km twin tunnels below river Hooghly in the East West Metro Project, in Kolkata! One of the company's biggest achievements in the area of underground metro infrastructure has been the successful completion of tunnelling for India's first underwater Metro project. The tunnelling was completed in just 67 days against the budgeted 127 days, which attests to the company's meticulous planning and efficient execution. These tunnels connect two of the world's busiest railway stations, Howrah and Sealdah. Once operational, the service will revolutionise travel in Kolkata, the first city in India to have an underground metro. Taking stock While tunnelling has been done under rivers across the world, and some projects have met with success, Afcons was faced with several challenges when it took up a project of this magnitude. Detailed investigations, case studies, planning, design considerations and logistic arrangements were carried out before the tunnel-boring machines (TBMs) could plunge below the river. What made the East West Metro Project even tougher was the alignment. It passes through challenging topography, necessitating tunnelling in the vicinity or directly below dilapidated buildings, railway offices, a busy and packed railway yard, busy roads, bridges and flyovers and heritage monuments. The geology of Kolkata and Howrah is erratic, especially the topmost stratum, which is soft and weak, adding to the challenge. Precise planning The engineers focussed on selecting suitable designs and technologies for the successful delivery of the project. The designing of this project was entrusted to specialised world-class design companies such as Atkins, Systra and Tunnelconsult. Afcons chose Herrenkeneckht TBMs for this project, based on its track record in manufacturing machines tailor-made for specific project requirements. HK is also engaged in the maintenance of the two TBMs deployed for the Kolkata Metro project. While Kolkata Metro Rail Corporation (KMRCL) carried out soil investigation work at the pre-tender stage for feasibility study, Afcons carried out soil investigation work near the entire tunnel alignment, deploying floating barges and pontoons in the river portion. The company also conducted extensive surveys of the buildings in proximity to the alignment before carrying out tunnelling. Unique challenges While executing this project, the tunnel crew faced the unique problem of the TBMs moving through soft clay strata at a lesser depth over structures that are almost a century old. Some of them are ravaged to the extent of being dilapidated. Apart from the main Colvin Court building, the TBMs passed below the quarters for service staff, which are in poor shape. These structures house high-ranking Railways officials. Another issue of concern was mining below Howrah Railway Yard, one of the busiest railway yards in the country with over 670 running trains and a footfall of 10.5 lakh daily. Boring below these structures was a herculean task. Mining had to be done over 350 m below the yard for each tunnel. The TBMs had to negotiate a sharp curve of radius 228 m, plunging into a new geology (stiff clay) and passed by the Bankim Setu piers. There are only a few comparable examples of such a tight curve undertaken in India. One more curve of 226 m radius was achieved near Rajbhawan before Esplanade Station. Obtaining CRS approvals for the project was another gigantic task, and this was achieved after satisfactory closure of all requirements. The procedure was hectic, but it helped gain several insights into project management during the tunnelling operation. Key innovations Afcons deployed a highly experienced tunnel crew on board, should an entry into the cutting chamber be required under high hyperbaric pressures. In the remote possibility of river water ingress, the TBMs could shut down like a submarine for safe evacuation. A project of this scale involves a number of innovations and the engineers improved upon numerous processes while planning the project. Owing to site constraints, the TBMs had to be driven through Howrah station in advance. This was a delicate operation, where they could encounter difficulty in crossing the diaphragm walls. Afcons designed a 'soft eye' of Styrofoam replacing M-40 concrete, which worked extremely well for this project. This is a first-of-its-kind attempted in India by in-house design engineers. Relief measures Special efforts were made to ensure that there was no loss of life and property during the TBM operations. More than five teams were deployed to carry out extensive repairs in all critical buildings. There was no compromise on safety, with adequate traffic diversions, restricted pedestrian movements and timely evacuations. About 300 people were relocated to hotels during tunnelling operation near their premises, and were brought back safely to their homes after the task was completed. This gesture won Afcons accolades from the public, government authorities, and others, and set new standards in project management. Last-minute risks This project has been a learning curve for Afcons. Underground tunnelling is in itself a challenging task, but underwater tunnelling is far more complex and risky. The chances of water ingress are high and so are the possibilities of geological surprises owing to the impact of tunnelling. Once the tunnelling began under the riverbed, the team ensured it did not stop under any circumstances. In underwater tunnelling, the bore had to be dug much deeper owing to the possibility of water inflow. This required a high level of detailing, precision and preparation. The meticulous planning bore fruit with the TBMs crossing the river seamlessly covering a distance of 11-12 m daily. About the author: Virender Kaul is Project Manager of East West Metro Project, Kolkata. Share your views on this article at [email protected]

Next Story
Infrastructure Urban

DoT Launches Financial Fraud Risk Indicator to Boost Cybersecurity

In a major step towards combating cyber fraud and financial crime, the Department of Telecommunications (DoT) has announced sharing of 鈥淔inancial Fraud Risk Indicator (FRI)鈥� with stakeholders- an output from a multi- dimensional analytical tool developed as part of the Digital Intelligence Platform (DIP) to empower financial institutions with advance actionable intelligence for cyber fraud prevention. This will enhance cyber protection and validation checks in case of mobile numbers flagged with this tool when digital payment is proposed to be made to such numbers.What is the 鈥淔inancial ..

Next Story
Infrastructure Urban

Bengaluru鈥檚 Flood Risk Grows: Urgent Need for Infrastructure Upgrades

Bengaluru, one of India鈥檚 fastest-growing cities, has witnessed an average economic growth rate of 8.5 per cent over the past decade. As a major economic hub, it hosts diverse sectors such as technology, banking, consulting, defence, and R&D. However, this rapid development has led to large-scale urbanisation and a significant population influx, severely straining the city's natural ecosystem鈥攅specially its drainage infrastructure鈥攍eading to recurring urban flooding. Bengaluru鈥檚 primary stormwater channels, known as Rajakaluves, were originally built to manage stormwater by co..

Next Story
Infrastructure Urban

WACKER Opens New Specialty Silicone Plants in China

WACKER is responding to rising demand for high-quality specialty silicones in China by expanding its production capacities at its Zhangjiagang site. The Group held a ceremony today to celebrate the mechanical completion of the facilities. Going forward, the new production complex will manufacture silicone fluids, silicone emulsions and silicone elastomer gels. Production is to be ramped up over the coming months. As planned, WACKER has invested a low three-digit million euro amount in the expansion project.鈥淥ur investment here in Zhangjiagang shows that we are committed to our successful 鈥�..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement