ÑDz©ÌåÓý¹ÙÍøÊ×Ò³

Reduction of Cycle Time by Implementing Value Stream Mapping
OIL & GAS

Reduction of Cycle Time by Implementing Value Stream Mapping

The construction industry suffers a great deal from time and cost overruns. One of the key causes for such uncertainties in projects is following traditional construction practices. This case study deals with one of URCC’s projects where the cycle time of the ‘I� girder erection process has been reduced from 11 days to four by implementing an appropriate Lean approach, Value Stream Mapping (VSM).

Background

URCC was awarded the building of a prime facility for Verbio India Pvt Ltd in Punjab. Verbio is a German-based company that specialises in biogas production.

The project involved the construction of eight air and watertight gas fermenter silos. The silos are positioned parallel to each other, in which four silos are in Line 1, and four are in Line 2.

The biogas fermenter silos are generally larger in dimension; hence, erecting the precast structures gets tedious. The main issue the team faced in this case was the generation of ‘time waste� while erecting and placing the I girder and planks on top of the eight RCC silos, which are about 20 m in height with a 26-m radius. However, the team tackled this challenge by implementing an effective Lean tool: VSM.

Need for study

  • To improve planning and proper allocation of resources
  • To reduce equipment idle time and increase productivity
  • Objective

    The main objective of this study is to reduce the cycle time of the erection process by implementing a Lean approach, VSM.

    Method

    After an in-depth study of the problem statement, the team selected an appropriate Lean tool, VSM. As it is a visualisation tool, it helped them to understand their current state at the initial stage of implementation. Post the implementation they managed to improve the overall process by developing future state maps.

    Methodology

  • Step 1: The existing critical path activity (erection of I girder) of the project was studied
  • Step 2: Preparation of the current state map of silos 1.1 and 1.2
  • Step 3: Analysis of current state map and identification of waste
  • Step 4: After eliminating the waste, a future state map was prepared for silos 3.1, 4.1, 1.2, 2.2, 3.2 & 4.2
  • Step 5: Implementation of the developed future state map
  • Step 6: Improvement in productivity was measured.
  • Result

    Implementing this effective Lean tool, VSM has helped the project team reduce the cycle time from 11 days to four; i.e. around 64 per cent of the project timeline has been reduced. This eventually resulted in the reduction of the total cost of the erection process from INR 694,200 to INR 222,800.

    About the author: Ragavi Prabaharan is Lean Coordinator at URC Construction.

    The construction industry suffers a great deal from time and cost overruns. One of the key causes for such uncertainties in projects is following traditional construction practices. This case study deals with one of URCC’s projects where the cycle time of the ‘I� girder erection process has been reduced from 11 days to four by implementing an appropriate Lean approach, Value Stream Mapping (VSM). Background URCC was awarded the building of a prime facility for Verbio India Pvt Ltd in Punjab. Verbio is a German-based company that specialises in biogas production. The project involved the construction of eight air and watertight gas fermenter silos. The silos are positioned parallel to each other, in which four silos are in Line 1, and four are in Line 2. The biogas fermenter silos are generally larger in dimension; hence, erecting the precast structures gets tedious. The main issue the team faced in this case was the generation of ‘time waste� while erecting and placing the I girder and planks on top of the eight RCC silos, which are about 20 m in height with a 26-m radius. However, the team tackled this challenge by implementing an effective Lean tool: VSM. Need for study To improve planning and proper allocation of resources To reduce equipment idle time and increase productivity Objective The main objective of this study is to reduce the cycle time of the erection process by implementing a Lean approach, VSM. Method After an in-depth study of the problem statement, the team selected an appropriate Lean tool, VSM. As it is a visualisation tool, it helped them to understand their current state at the initial stage of implementation. Post the implementation they managed to improve the overall process by developing future state maps. Methodology Step 1: The existing critical path activity (erection of I girder) of the project was studied Step 2: Preparation of the current state map of silos 1.1 and 1.2 Step 3: Analysis of current state map and identification of waste Step 4: After eliminating the waste, a future state map was prepared for silos 3.1, 4.1, 1.2, 2.2, 3.2 & 4.2 Step 5: Implementation of the developed future state map Step 6: Improvement in productivity was measured. Result Implementing this effective Lean tool, VSM has helped the project team reduce the cycle time from 11 days to four; i.e. around 64 per cent of the project timeline has been reduced. This eventually resulted in the reduction of the total cost of the erection process from INR 694,200 to INR 222,800. About the author: Ragavi Prabaharan is Lean Coordinator at URC Construction.

    Next Story
    Real Estate

    Kolkata’s luxury housing market sees price growth amid mixed trends

    A new study by Nklusive reveals that Kolkata’s luxury residential market (Rs 5�10 crore) recorded a 33 per cent year-on-year rise in supply and a 52 per cent increase in sales in calendar year 2024 (CY24). South Kolkata led with 78 per cent of the segment’s supply. The average price rose by 6 per cent—from Rs 17,519 to Rs 18,600 per sq ft—while unsold inventory grew by 15 per cent. Monthly absorption improved from 2 to 3 units.In contrast, the ultra-luxury segment (Rs 10 crore and above) experienced a 17 per cent decline in supply and a 30 per cent fall in sales. Central Kolkata acco..

    Next Story
    Infrastructure Transport

    New Expressway to Cut Pune-Bengaluru Travel Time by Half

    The upcoming Pune-Bengaluru Expressway is expected to significantly improve connectivity and economic opportunities across Maharashtra and Karnataka. This 700-kilometre greenfield, access-controlled highway will cut the travel time between Pune and Bengaluru from 15 hours to just 7 hours, facilitating easier movement for both commuters and businesses. Starting from Bommanal in Karnataka’s Athani Taluk, the expressway will traverse important districts such as Belagavi, Bagalkot, and Jamakhandi. It will then enter Maharashtra at Kanjle, connect with the proposed Pune Ring Road, and pass throug..

    Next Story
    Infrastructure Transport

    Nagpur’s Koradi Naka to Get Y-Shaped Flyover for Safer, Smoother Traffic

    To alleviate traffic congestion and enhance safety at Koradi Naka in Nagpur, a Y-shaped flyover is currently being constructed on National Highway 47. Demolition work has already commenced, with the main construction scheduled to start on June 20, 2025.The project, costing Rs 430.37 billion, involves building a 1,090-meter-long flyover that will connect Farsa, the Mahadula Railway Overbridge (ROB), and Bokhara Road, and will also feature an underpass. The existing structure will be repurposed into a service road to facilitate local traffic.Koradi Naka has been identified as a significant "blac..

    Advertisement

    Advertisement

    Subscribe to Our Newsletter

    Get daily newsletters around different themes from Construction world.

    STAY CONNECTED

    Advertisement

    Advertisement

    Advertisement

    Advertisement