Kerala government to implement Sabarimala airport project
22 Sep 2021
3 Min Read
CW Team
Despite the queries raised by the Ministry of Civil Aviation (MoCA) on the planned airport project at Sabarimala, the government will execute the project.
The government began preparations for the site survey, and a drone survey of Cheruvally estate has been allotted for the project.
On September 8, a review meeting held by CM Pinarayi Vijayan had evaluated the project, reviewed its status and the measures that need to be taken promptly to expedite its execution.
Quoting the views of the director general of civil aviation (DGCA), the Ministry of civil aviation had asked for some clarifications from the government regarding the application for project approval. A decision was taken during the CM鈥檚 review to provide a reply in this regard. Ministry of defence approval is anticipated soon since the Indian Air Force (IAF) has conveyed that it has no problem giving site permission.
But, a social impact assessment study, soil test could not be conducted because of pending litigations on ownership of the designated land. Whatever MoCA stated in the letter quoting DGCA鈥檚 report is part of routine administrative communication. The letter itself shows that despite the guidelines on greenfield airports that the planned airport may not meet, the project still can be approved by the government.
The proposed site will need a considerable amount of preparatory work to make it suitable for the project. According to the environmental impact assessment report provided by the consultant Louis Berger Consulting Pvt Ltd, a preliminary analysis of the site topography shows that the current elevation ranges from 40 m to 170 m, while the current average mean elevation is about 112 m.
The observed site is challenging in terms of grading requirements since there is a vast difference between maximum and minimum elevation. The fundamental part of the project site is at a higher elevation, while the boundaries are at a lower elevation. Current topography comprises moderately-high to steep slopes in a considerable area of the project site.
The consultant told the media that it has been assessed that 130 structures and five common property resources will be affected (approximately), comprising a temple, a church, a mosque and a hospital. The airport, which is considered to have 800 passengers by 2029-30 and 1,850 passengers during peak hours by 2049-50, is likely to break even only in 60 years. It raises many questions about the economic viability of the project.
Also read:
DCGA issues Aerodrome license to IRB Sindhudurg Airport
Despite the queries raised by the Ministry of Civil Aviation (MoCA) on the planned airport project at Sabarimala, the government will execute the project.
The government began preparations for the site survey, and a drone survey of Cheruvally estate has been allotted for the project.
On September 8, a review meeting held by CM Pinarayi Vijayan had evaluated the project, reviewed its status and the measures that need to be taken promptly to expedite its execution.
Quoting the views of the director general of civil aviation (DGCA), the Ministry of civil aviation had asked for some clarifications from the government regarding the application for project approval. A decision was taken during the CM鈥檚 review to provide a reply in this regard. Ministry of defence approval is anticipated soon since the Indian Air Force (IAF) has conveyed that it has no problem giving site permission.
But, a social impact assessment study, soil test could not be conducted because of pending litigations on ownership of the designated land. Whatever MoCA stated in the letter quoting DGCA鈥檚 report is part of routine administrative communication. The letter itself shows that despite the guidelines on greenfield airports that the planned airport may not meet, the project still can be approved by the government.
The proposed site will need a considerable amount of preparatory work to make it suitable for the project. According to the environmental impact assessment report provided by the consultant Louis Berger Consulting Pvt Ltd, a preliminary analysis of the site topography shows that the current elevation ranges from 40 m to 170 m, while the current average mean elevation is about 112 m.
The observed site is challenging in terms of grading requirements since there is a vast difference between maximum and minimum elevation. The fundamental part of the project site is at a higher elevation, while the boundaries are at a lower elevation. Current topography comprises moderately-high to steep slopes in a considerable area of the project site.
The consultant told the media that it has been assessed that 130 structures and five common property resources will be affected (approximately), comprising a temple, a church, a mosque and a hospital. The airport, which is considered to have 800 passengers by 2029-30 and 1,850 passengers during peak hours by 2049-50, is likely to break even only in 60 years. It raises many questions about the economic viability of the project.
Image SourceAlso read: DCGA issues Aerodrome license to IRB Sindhudurg Airport
Next Story
Kolkata鈥檚 luxury housing market sees price growth amid mixed trends
A new study by Nklusive reveals that Kolkata鈥檚 luxury residential market (Rs 5鈥�10 crore) recorded a 33 per cent year-on-year rise in supply and a 52 per cent increase in sales in calendar year 2024 (CY24). South Kolkata led with 78 per cent of the segment鈥檚 supply. The average price rose by 6 per cent鈥攆rom Rs 17,519 to Rs 18,600 per sq ft鈥攚hile unsold inventory grew by 15 per cent. Monthly absorption improved from 2 to 3 units.In contrast, the ultra-luxury segment (Rs 10 crore and above) experienced a 17 per cent decline in supply and a 30 per cent fall in sales. Central Kolkata acco..
Next Story
New Expressway to Cut Pune-Bengaluru Travel Time by Half
The upcoming Pune-Bengaluru Expressway is expected to significantly improve connectivity and economic opportunities across Maharashtra and Karnataka. This 700-kilometre greenfield, access-controlled highway will cut the travel time between Pune and Bengaluru from 15 hours to just 7 hours, facilitating easier movement for both commuters and businesses. Starting from Bommanal in Karnataka鈥檚 Athani Taluk, the expressway will traverse important districts such as Belagavi, Bagalkot, and Jamakhandi. It will then enter Maharashtra at Kanjle, connect with the proposed Pune Ring Road, and pass throug..
Next Story
Nagpur鈥檚 Koradi Naka to Get Y-Shaped Flyover for Safer, Smoother Traffic
To alleviate traffic congestion and enhance safety at Koradi Naka in Nagpur, a Y-shaped flyover is currently being constructed on National Highway 47. Demolition work has already commenced, with the main construction scheduled to start on June 20, 2025.The project, costing Rs 430.37 billion, involves building a 1,090-meter-long flyover that will connect Farsa, the Mahadula Railway Overbridge (ROB), and Bokhara Road, and will also feature an underpass. The existing structure will be repurposed into a service road to facilitate local traffic.Koradi Naka has been identified as a significant "blac..