Rajpath Infracon creates record by constructing 39.69 km Road in 24 hrs
ROADS & HIGHWAYS

Rajpath Infracon creates record by constructing 39.69 km Road in 24 hrs

On 31st May 2021 Pune-based private firm, Rajpath Infracon created a World Record by constructing 39.691 kms of Asphalt road in 24 hours. This record was achieved on Pusegaon 鈥� Mhasurne Road, Satara District, Maharashtra with the help of Maharashtra state government鈥檚 public works department (PWD). In order to celebrate this massive success the Builders鈥� Association of India (All India Association of Civil Engineering Construction Contractors and Builders) in Association with BAI, Pune Centre organised a virtual meet on 26 June.

Jagdish Kadam, director, Rajpath Infracon Pvt Ltd was the keynote speaker and Ram Nivas Gupta, President, BAI as the Chief Guest of the virtual meet. Ulhas Debadwar, Secretary, PWD, Government of Maharashtra was the Guest of Honour. And Ranjeet More, Past Chairman, BAI, Pune Centre and Past Vice President, BAI was the Convener of the meet.

In the virtual meet Jagdish Kadam took the participants through the planning and execution stages of the Asphalt Road construction.

PWD has given contract to Rajpath Infracon, which had set to construct a 30 km of road in a day. However, the team constructed 39.69 km of roads in a day between 7 am on Sunday (May 30) and 7 am on Monday (May 31) in 24 hours.

The entire project was completed in three shifts and at six locations, fifteen Civil Engineers of PWD, sixty Civil Engineers of Rajpath Infracon, forty seven Supervisors, twenty three Quality Control Engineers, 150 Drivers, 110 labourers etc. were engaged. Some of the major machinery deputed were 鈥� eight modern Hot Mix Batch Plants, seven Sensor Pavers, twelve Vibratory Rollers, six Pneumatic Rollers, 180 Hyas, etc. 6000 cu mtr metal and 1100 MT Asphalt were used. One lane of road was completed using bituminous concrete (BC).

The road was three and a half metres wide and 39.69 kilometres long covering Pusegaon, Jaigaon, Aundh, Gopuj and Mhasurne. The initiative was carried out in compliance with the rules laid down by the central and state governments regarding Covid-19. Also, Rajpath Infracon took care of all precautionary measures.

The initiative was carried out in compliance with the rules laid down by the central and state governments regarding Covid-19. Also, Rajpath Infracon took care of all precautionary measures.

Jagdish Kadam said, 鈥淲eek seek opportunity in adversity. The Covid Situation was a big challenge for us, we had to maintain proper social distancing and the entire team had to go through rapid testing. But for our machinery, lockdown was a boon as they could safely travel in empty roads to the site.鈥�

Ulhas Deebadwar, Secretary, PWD added how the involvement of the staff, family, government officials and the ministries throughout the project helped them a lot and the work was very smooth. There were weather constraints and strict Covid restrictions, but the team was high in confidence.

On 31st May 2021 Pune-based private firm, Rajpath Infracon created a World Record by constructing 39.691 kms of Asphalt road in 24 hours. This record was achieved on Pusegaon 鈥� Mhasurne Road, Satara District, Maharashtra with the help of Maharashtra state government鈥檚 public works department (PWD). In order to celebrate this massive success the Builders鈥� Association of India (All India Association of Civil Engineering Construction Contractors and Builders) in Association with BAI, Pune Centre organised a virtual meet on 26 June. Jagdish Kadam, director, Rajpath Infracon Pvt Ltd was the keynote speaker and Ram Nivas Gupta, President, BAI as the Chief Guest of the virtual meet. Ulhas Debadwar, Secretary, PWD, Government of Maharashtra was the Guest of Honour. And Ranjeet More, Past Chairman, BAI, Pune Centre and Past Vice President, BAI was the Convener of the meet. In the virtual meet Jagdish Kadam took the participants through the planning and execution stages of the Asphalt Road construction. PWD has given contract to Rajpath Infracon, which had set to construct a 30 km of road in a day. However, the team constructed 39.69 km of roads in a day between 7 am on Sunday (May 30) and 7 am on Monday (May 31) in 24 hours. The entire project was completed in three shifts and at six locations, fifteen Civil Engineers of PWD, sixty Civil Engineers of Rajpath Infracon, forty seven Supervisors, twenty three Quality Control Engineers, 150 Drivers, 110 labourers etc. were engaged. Some of the major machinery deputed were 鈥� eight modern Hot Mix Batch Plants, seven Sensor Pavers, twelve Vibratory Rollers, six Pneumatic Rollers, 180 Hyas, etc. 6000 cu mtr metal and 1100 MT Asphalt were used. One lane of road was completed using bituminous concrete (BC). The road was three and a half metres wide and 39.69 kilometres long covering Pusegaon, Jaigaon, Aundh, Gopuj and Mhasurne. The initiative was carried out in compliance with the rules laid down by the central and state governments regarding Covid-19. Also, Rajpath Infracon took care of all precautionary measures. The initiative was carried out in compliance with the rules laid down by the central and state governments regarding Covid-19. Also, Rajpath Infracon took care of all precautionary measures. Jagdish Kadam said, 鈥淲eek seek opportunity in adversity. The Covid Situation was a big challenge for us, we had to maintain proper social distancing and the entire team had to go through rapid testing. But for our machinery, lockdown was a boon as they could safely travel in empty roads to the site.鈥� Ulhas Deebadwar, Secretary, PWD added how the involvement of the staff, family, government officials and the ministries throughout the project helped them a lot and the work was very smooth. There were weather constraints and strict Covid restrictions, but the team was high in confidence.

Next Story
Infrastructure Transport

New Expressway to Cut Pune-Bengaluru Travel Time by Half

The upcoming Pune-Bengaluru Expressway is expected to significantly improve connectivity and economic opportunities across Maharashtra and Karnataka. This 700-kilometre greenfield, access-controlled highway will cut the travel time between Pune and Bengaluru from 15 hours to just 7 hours, facilitating easier movement for both commuters and businesses. Starting from Bommanal in Karnataka鈥檚 Athani Taluk, the expressway will traverse important districts such as Belagavi, Bagalkot, and Jamakhandi. It will then enter Maharashtra at Kanjle, connect with the proposed Pune Ring Road, and pass throug..

Next Story
Infrastructure Transport

Nagpur鈥檚 Koradi Naka to Get Y-Shaped Flyover for Safer, Smoother Traffic

To alleviate traffic congestion and enhance safety at Koradi Naka in Nagpur, a Y-shaped flyover is currently being constructed on National Highway 47. Demolition work has already commenced, with the main construction scheduled to start on June 20, 2025.The project, costing Rs 430.37 billion, involves building a 1,090-meter-long flyover that will connect Farsa, the Mahadula Railway Overbridge (ROB), and Bokhara Road, and will also feature an underpass. The existing structure will be repurposed into a service road to facilitate local traffic.Koradi Naka has been identified as a significant "blac..

Next Story
Infrastructure Transport

Avinashi Flyover: Huge Iron Span to be Placed Over Railway Overbridge

A senior official from the Special Project Wing explained that a concrete deck of such length was not practical across active railway lines. Therefore, the department had decided to opt for a specially fabricated iron span.With the span now ready, its installation is awaiting railway clearance. The Salem Division of Southern Railway has already given its approval, while the final clearance is still pending from the Southern Railway headquarters in Chennai. For the installation process, railway operations under the ROB will need to be suspended for at least five days.The official also mentioned..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement