Bullet train project's land acquisition set to finish by end of March
08 Mar 2024
2 Min Read
CW Team
Officials have indicated that the Centre aims to finalize land acquisition for the Rs 1 trillion bullet train project by the end of this month. It has been disclosed that the Chief Secretary of Maharashtra has instructed all district collectors in the state to hand over land for the project within the adjusted timeline.
Furthermore, they mentioned that the work on shifting transmission lines should also be concluded by the end of March 2024. The bullet train project encompasses areas in Gujarat, Dadra and Nagar Haveli, and Maharashtra.
In Gujarat and Dadra and Nagar Haveli, the process of land acquisition and possession has been successfully completed. However, in Maharashtra, over 15% of the total land required is yet to be transferred to the National High Speed Rail Corporation (NHSRCL). The land acquired amounts to 959.04 hectares in Gujarat and 430.45 hectares in Maharashtra.
The NHSRCL, functioning as a Special Purpose Vehicle (SPV), has 50% equity from the Railways Ministry and 25% each from the Maharashtra and Gujarat state governments. Apart from land acquisition, the prompt completion of power transmission line shifting is crucial to meet the revised project timelines. Gujarat has made significant progress by completing the shifting of 1333 infringing lines.
In Maharashtra, there are 318 infringing lines, of which approximately 300 have been dealt with so far. According to a senior official, the remaining transmission lines in Maharashtra will also be relocated by the end of March 2024. The project has obtained approvals for activities such as forest, wildlife, and mangroves cutting, in addition to tree cutting.
Officials have indicated that the Centre aims to finalize land acquisition for the Rs 1 trillion bullet train project by the end of this month. It has been disclosed that the Chief Secretary of Maharashtra has instructed all district collectors in the state to hand over land for the project within the adjusted timeline.
Furthermore, they mentioned that the work on shifting transmission lines should also be concluded by the end of March 2024. The bullet train project encompasses areas in Gujarat, Dadra and Nagar Haveli, and Maharashtra.
In Gujarat and Dadra and Nagar Haveli, the process of land acquisition and possession has been successfully completed. However, in Maharashtra, over 15% of the total land required is yet to be transferred to the National High Speed Rail Corporation (NHSRCL). The land acquired amounts to 959.04 hectares in Gujarat and 430.45 hectares in Maharashtra.
The NHSRCL, functioning as a Special Purpose Vehicle (SPV), has 50% equity from the Railways Ministry and 25% each from the Maharashtra and Gujarat state governments. Apart from land acquisition, the prompt completion of power transmission line shifting is crucial to meet the revised project timelines. Gujarat has made significant progress by completing the shifting of 1333 infringing lines.
In Maharashtra, there are 318 infringing lines, of which approximately 300 have been dealt with so far. According to a senior official, the remaining transmission lines in Maharashtra will also be relocated by the end of March 2024. The project has obtained approvals for activities such as forest, wildlife, and mangroves cutting, in addition to tree cutting.
Next Story
Kolkata鈥檚 luxury housing market sees price growth amid mixed trends
A new study by Nklusive reveals that Kolkata鈥檚 luxury residential market (Rs 5鈥�10 crore) recorded a 33 per cent year-on-year rise in supply and a 52 per cent increase in sales in calendar year 2024 (CY24). South Kolkata led with 78 per cent of the segment鈥檚 supply. The average price rose by 6 per cent鈥攆rom Rs 17,519 to Rs 18,600 per sq ft鈥攚hile unsold inventory grew by 15 per cent. Monthly absorption improved from 2 to 3 units.In contrast, the ultra-luxury segment (Rs 10 crore and above) experienced a 17 per cent decline in supply and a 30 per cent fall in sales. Central Kolkata acco..
Next Story
New Expressway to Cut Pune-Bengaluru Travel Time by Half
The upcoming Pune-Bengaluru Expressway is expected to significantly improve connectivity and economic opportunities across Maharashtra and Karnataka. This 700-kilometre greenfield, access-controlled highway will cut the travel time between Pune and Bengaluru from 15 hours to just 7 hours, facilitating easier movement for both commuters and businesses. Starting from Bommanal in Karnataka鈥檚 Athani Taluk, the expressway will traverse important districts such as Belagavi, Bagalkot, and Jamakhandi. It will then enter Maharashtra at Kanjle, connect with the proposed Pune Ring Road, and pass throug..
Next Story
Nagpur鈥檚 Koradi Naka to Get Y-Shaped Flyover for Safer, Smoother Traffic
To alleviate traffic congestion and enhance safety at Koradi Naka in Nagpur, a Y-shaped flyover is currently being constructed on National Highway 47. Demolition work has already commenced, with the main construction scheduled to start on June 20, 2025.The project, costing Rs 430.37 billion, involves building a 1,090-meter-long flyover that will connect Farsa, the Mahadula Railway Overbridge (ROB), and Bokhara Road, and will also feature an underpass. The existing structure will be repurposed into a service road to facilitate local traffic.Koradi Naka has been identified as a significant "blac..