Telangana: Rail work to YTPS done, coal transportation to start soon
30 Oct 2024
2 Min Read
CW Team
The railway officials conducted a trial run on the new railway line constructed from Vishnupuram to Yadadri Thermal Power Plant (YTPS) in Damaracherla mandal of Nalgonda district.
The work of the 8 km railway line was completed recently, paving the way for coal transportation to the power plant.
According to officials, this particular line had been connected to Secunderabad-Guntur and Motumarri-Jaggayyapet routes for smooth transportation of coal to the plant.
Construction of an overpass and two sub-lines was underway near Damaracherla, the officials said, adding that about 50,000 metric tonnes of coal was needed on a regular basis and ten rakes would be moving in and out on this line.
According to sources, the signaling system at Vishnupuram railway station was supposed to be completed by October 1, but due to repair work on Balharshah-Kazipet-Vijayawada railway line, some trains were diverted to the Bibinagar-Nadikudi route, which caused a delay in changing the signaling system at Vishnupuram.
Since the railway line works have been completed, the officials are expecting the commissioning of the two units of the plant shortly.
As part of testing the readiness for full production of power, two boiler units were ‘fired� in May. It would take about five to six months before all the testing was completed to ensure every section of the two 800 MW units were working in synchrony, officials said, adding that once that was done, Unit I and Unit II would be ready for the commercial production of thermal power.
The Genco has set a deadline for Bharat Heavy Electricals Limited (BHEL), which is executing the project, to commission two units of Stage I by October and the three units of Stage II by March 2025. Due to delays in the construction of the railway line, the commissioning of the two units is likely to take place in November.
Although all five units should have been commissioned by October last year, there has been a time overrun for all five units. As the construction of the plant has already been delayed for more than three years, Genco is concerned that further delays will result in additional financial losses.
The project, when completed, is expected to cost around Rs 345.42 billion.
(By Telangana Today)
The railway officials conducted a trial run on the new railway line constructed from Vishnupuram to Yadadri Thermal Power Plant (YTPS) in Damaracherla mandal of Nalgonda district.
The work of the 8 km railway line was completed recently, paving the way for coal transportation to the power plant.
According to officials, this particular line had been connected to Secunderabad-Guntur and Motumarri-Jaggayyapet routes for smooth transportation of coal to the plant.
Construction of an overpass and two sub-lines was underway near Damaracherla, the officials said, adding that about 50,000 metric tonnes of coal was needed on a regular basis and ten rakes would be moving in and out on this line.
According to sources, the signaling system at Vishnupuram railway station was supposed to be completed by October 1, but due to repair work on Balharshah-Kazipet-Vijayawada railway line, some trains were diverted to the Bibinagar-Nadikudi route, which caused a delay in changing the signaling system at Vishnupuram.
Since the railway line works have been completed, the officials are expecting the commissioning of the two units of the plant shortly.
As part of testing the readiness for full production of power, two boiler units were ‘fired� in May. It would take about five to six months before all the testing was completed to ensure every section of the two 800 MW units were working in synchrony, officials said, adding that once that was done, Unit I and Unit II would be ready for the commercial production of thermal power.
The Genco has set a deadline for Bharat Heavy Electricals Limited (BHEL), which is executing the project, to commission two units of Stage I by October and the three units of Stage II by March 2025. Due to delays in the construction of the railway line, the commissioning of the two units is likely to take place in November.
Although all five units should have been commissioned by October last year, there has been a time overrun for all five units. As the construction of the plant has already been delayed for more than three years, Genco is concerned that further delays will result in additional financial losses.
The project, when completed, is expected to cost around Rs 345.42 billion.
(By Telangana Today)
Next Story
Kolkata’s luxury housing market sees price growth amid mixed trends
A new study by Nklusive reveals that Kolkata’s luxury residential market (Rs 5�10 crore) recorded a 33 per cent year-on-year rise in supply and a 52 per cent increase in sales in calendar year 2024 (CY24). South Kolkata led with 78 per cent of the segment’s supply. The average price rose by 6 per cent—from Rs 17,519 to Rs 18,600 per sq ft—while unsold inventory grew by 15 per cent. Monthly absorption improved from 2 to 3 units.In contrast, the ultra-luxury segment (Rs 10 crore and above) experienced a 17 per cent decline in supply and a 30 per cent fall in sales. Central Kolkata acco..
Next Story
New Expressway to Cut Pune-Bengaluru Travel Time by Half
The upcoming Pune-Bengaluru Expressway is expected to significantly improve connectivity and economic opportunities across Maharashtra and Karnataka. This 700-kilometre greenfield, access-controlled highway will cut the travel time between Pune and Bengaluru from 15 hours to just 7 hours, facilitating easier movement for both commuters and businesses. Starting from Bommanal in Karnataka’s Athani Taluk, the expressway will traverse important districts such as Belagavi, Bagalkot, and Jamakhandi. It will then enter Maharashtra at Kanjle, connect with the proposed Pune Ring Road, and pass throug..
Next Story
Nagpur’s Koradi Naka to Get Y-Shaped Flyover for Safer, Smoother Traffic
To alleviate traffic congestion and enhance safety at Koradi Naka in Nagpur, a Y-shaped flyover is currently being constructed on National Highway 47. Demolition work has already commenced, with the main construction scheduled to start on June 20, 2025.The project, costing Rs 430.37 billion, involves building a 1,090-meter-long flyover that will connect Farsa, the Mahadula Railway Overbridge (ROB), and Bokhara Road, and will also feature an underpass. The existing structure will be repurposed into a service road to facilitate local traffic.Koradi Naka has been identified as a significant "blac..