MahaRERA to make it easy for homebuyers to know exact project status
14 Jan 2022
3 Min Read
CW Team
MahaRERA recently released a circular making it compulsory for promoters to render certificates from architects, chartered accountants and engineers to the banks and with copies to the real estate regulatory authority before removing any amount realised from the home allottees noting that the withdrawal is in proportion to the percentage of work achieved.
The amount realised from allottees are deposited in a separate account. MahaRERA will upload the certificates rendered by the engineer and the architect on its website for the advantage of the home buyer.
亚博体育官网首页buyers will get to know the exact project status, like the amount of work attained and costs incurred, among other things. Earlier, the promoter had to get the certificates, but they were only required to render a self-declaration to the bank.
The promoters are additionally needed to obtain their separate account audited within six months after the end of every financial year by a chartered accountant and have to create a statement of accounts duly certified and inked by the chartered accountant. The audit will confirm that the amounts accumulated for a specific project have been used for the project and that the withdrawal complies with the proportion to the percentage of work finished.
The new regulation applies to both new projects as well as ongoing projects. Promoters under sub-section (2)(l) D of section 4 of the Act are needed to deposit 70% of the money that has been accumulated for the real estate project from the allottees, in a separate account in a scheduled bank, to cover the cost of construction, the land price and the amount so deposited can be utilised only for that objective.
To guarantee that the withdrawal is in proportion to the percentage of work achieved on the project, the promoter requires to present certificates from the architect, engineer and the chartered accountant to MahaRERA, apart from the bank, at the time of every withdrawal till the occupancy/ or completion certificate is obtained for the project.
The 2017 circular of the MahaRERA had enabled the promoter to only provide a self-declaration every quarter, rather than presenting these three certificates on each withdrawal to the bank. Advocate Anil D Souza, secretary of the MahaRERA Bar Association, told the media that MahaRERA has not just brought in more transparency into the financial aspect of the project management but additionally propelled greater accountability on promoters, along with the Architect, Engineer and CA certifying every stage.
Also read: MahaRERA asks realtors to declare mortgage of housing projects
MahaRERA recently released a circular making it compulsory for promoters to render certificates from architects, chartered accountants and engineers to the banks and with copies to the real estate regulatory authority before removing any amount realised from the home allottees noting that the withdrawal is in proportion to the percentage of work achieved.
The amount realised from allottees are deposited in a separate account. MahaRERA will upload the certificates rendered by the engineer and the architect on its website for the advantage of the home buyer.
亚博体育官网首页buyers will get to know the exact project status, like the amount of work attained and costs incurred, among other things. Earlier, the promoter had to get the certificates, but they were only required to render a self-declaration to the bank.
The promoters are additionally needed to obtain their separate account audited within six months after the end of every financial year by a chartered accountant and have to create a statement of accounts duly certified and inked by the chartered accountant. The audit will confirm that the amounts accumulated for a specific project have been used for the project and that the withdrawal complies with the proportion to the percentage of work finished.
The new regulation applies to both new projects as well as ongoing projects. Promoters under sub-section (2)(l) D of section 4 of the Act are needed to deposit 70% of the money that has been accumulated for the real estate project from the allottees, in a separate account in a scheduled bank, to cover the cost of construction, the land price and the amount so deposited can be utilised only for that objective.
To guarantee that the withdrawal is in proportion to the percentage of work achieved on the project, the promoter requires to present certificates from the architect, engineer and the chartered accountant to MahaRERA, apart from the bank, at the time of every withdrawal till the occupancy/ or completion certificate is obtained for the project.
The 2017 circular of the MahaRERA had enabled the promoter to only provide a self-declaration every quarter, rather than presenting these three certificates on each withdrawal to the bank. Advocate Anil D Souza, secretary of the MahaRERA Bar Association, told the media that MahaRERA has not just brought in more transparency into the financial aspect of the project management but additionally propelled greater accountability on promoters, along with the Architect, Engineer and CA certifying every stage.
Image Source
Also read: MahaRERA asks realtors to declare mortgage of housing projects
Next Story
Kolkata鈥檚 luxury housing market sees price growth amid mixed trends
A new study by Nklusive reveals that Kolkata鈥檚 luxury residential market (Rs 5鈥�10 crore) recorded a 33 per cent year-on-year rise in supply and a 52 per cent increase in sales in calendar year 2024 (CY24). South Kolkata led with 78 per cent of the segment鈥檚 supply. The average price rose by 6 per cent鈥攆rom Rs 17,519 to Rs 18,600 per sq ft鈥攚hile unsold inventory grew by 15 per cent. Monthly absorption improved from 2 to 3 units.In contrast, the ultra-luxury segment (Rs 10 crore and above) experienced a 17 per cent decline in supply and a 30 per cent fall in sales. Central Kolkata acco..
Next Story
New Expressway to Cut Pune-Bengaluru Travel Time by Half
The upcoming Pune-Bengaluru Expressway is expected to significantly improve connectivity and economic opportunities across Maharashtra and Karnataka. This 700-kilometre greenfield, access-controlled highway will cut the travel time between Pune and Bengaluru from 15 hours to just 7 hours, facilitating easier movement for both commuters and businesses. Starting from Bommanal in Karnataka鈥檚 Athani Taluk, the expressway will traverse important districts such as Belagavi, Bagalkot, and Jamakhandi. It will then enter Maharashtra at Kanjle, connect with the proposed Pune Ring Road, and pass throug..
Next Story
Nagpur鈥檚 Koradi Naka to Get Y-Shaped Flyover for Safer, Smoother Traffic
To alleviate traffic congestion and enhance safety at Koradi Naka in Nagpur, a Y-shaped flyover is currently being constructed on National Highway 47. Demolition work has already commenced, with the main construction scheduled to start on June 20, 2025.The project, costing Rs 430.37 billion, involves building a 1,090-meter-long flyover that will connect Farsa, the Mahadula Railway Overbridge (ROB), and Bokhara Road, and will also feature an underpass. The existing structure will be repurposed into a service road to facilitate local traffic.Koradi Naka has been identified as a significant "blac..