Pyramid Urban 亚博体育官网首页s residents complain about frequent power outages
24 Dec 2021
2 Min Read
CW Team
Power outages and voltage fluctuations have been reported by residents of Pyramid Urban 亚博体育官网首页s two in Sector 86.
According to the residents, their flats are served by 11 kV feeder lines. They claimed that despite collecting an average of Rs 50,000 per flat in electricity infrastructure development charges, the developer has yet to construct a 33 kV switching station. The result is daily power outages of two to three hours.
A temporary electricity connection of 11 kV has been obtained by the builder. Regular power outages occur here, causing hardship for those who work from home and interfering with children's studies.
Even in the winter, when consumption is lower, they are subjected to frequent power outages. The majority of the residents have installed inverters, but they occasionally run out of batteries, one of the residents, RK Jain, explained.
In December 2020, the developer began distributing flats to homeowners. The society, which has 863 apartments, is home to over 600 families. According to the families, they filed complaints about the situation, but neither the developer nor the electricity department paid attention to their concerns.
When asked about the 33 kV switching station, the developer never responds and is always evasive. The developer and the discom continue to blame each other.
In the case of electricity bills, there is no transparency. Another resident, Vijay Singh Saroa, said that they are charged Rs 6.5 per unit and give Rs 200 per month as fixed charges.
SDO Manesar Gaurav Dahiya said there is no shortage of power supply from their side. The 33 kV switching station must be built by all developers from sectors 58 to 115, either individually or in collaboration with other builders.
Power outages and voltage fluctuations have been reported by residents of Pyramid Urban 亚博体育官网首页s two in Sector 86.
According to the residents, their flats are served by 11 kV feeder lines. They claimed that despite collecting an average of Rs 50,000 per flat in electricity infrastructure development charges, the developer has yet to construct a 33 kV switching station. The result is daily power outages of two to three hours.
A temporary electricity connection of 11 kV has been obtained by the builder. Regular power outages occur here, causing hardship for those who work from home and interfering with children's studies.
Even in the winter, when consumption is lower, they are subjected to frequent power outages. The majority of the residents have installed inverters, but they occasionally run out of batteries, one of the residents, RK Jain, explained.
In December 2020, the developer began distributing flats to homeowners. The society, which has 863 apartments, is home to over 600 families. According to the families, they filed complaints about the situation, but neither the developer nor the electricity department paid attention to their concerns.
When asked about the 33 kV switching station, the developer never responds and is always evasive. The developer and the discom continue to blame each other.
In the case of electricity bills, there is no transparency. Another resident, Vijay Singh Saroa, said that they are charged Rs 6.5 per unit and give Rs 200 per month as fixed charges.
SDO Manesar Gaurav Dahiya said there is no shortage of power supply from their side. The 33 kV switching station must be built by all developers from sectors 58 to 115, either individually or in collaboration with other builders.
Image Source
Next Story
Kolkata鈥檚 luxury housing market sees price growth amid mixed trends
A new study by Nklusive reveals that Kolkata鈥檚 luxury residential market (Rs 5鈥�10 crore) recorded a 33 per cent year-on-year rise in supply and a 52 per cent increase in sales in calendar year 2024 (CY24). South Kolkata led with 78 per cent of the segment鈥檚 supply. The average price rose by 6 per cent鈥攆rom Rs 17,519 to Rs 18,600 per sq ft鈥攚hile unsold inventory grew by 15 per cent. Monthly absorption improved from 2 to 3 units.In contrast, the ultra-luxury segment (Rs 10 crore and above) experienced a 17 per cent decline in supply and a 30 per cent fall in sales. Central Kolkata acco..
Next Story
New Expressway to Cut Pune-Bengaluru Travel Time by Half
The upcoming Pune-Bengaluru Expressway is expected to significantly improve connectivity and economic opportunities across Maharashtra and Karnataka. This 700-kilometre greenfield, access-controlled highway will cut the travel time between Pune and Bengaluru from 15 hours to just 7 hours, facilitating easier movement for both commuters and businesses. Starting from Bommanal in Karnataka鈥檚 Athani Taluk, the expressway will traverse important districts such as Belagavi, Bagalkot, and Jamakhandi. It will then enter Maharashtra at Kanjle, connect with the proposed Pune Ring Road, and pass throug..
Next Story
Nagpur鈥檚 Koradi Naka to Get Y-Shaped Flyover for Safer, Smoother Traffic
To alleviate traffic congestion and enhance safety at Koradi Naka in Nagpur, a Y-shaped flyover is currently being constructed on National Highway 47. Demolition work has already commenced, with the main construction scheduled to start on June 20, 2025.The project, costing Rs 430.37 billion, involves building a 1,090-meter-long flyover that will connect Farsa, the Mahadula Railway Overbridge (ROB), and Bokhara Road, and will also feature an underpass. The existing structure will be repurposed into a service road to facilitate local traffic.Koradi Naka has been identified as a significant "blac..