Runwal 亚博体育官网首页s to pay Rs 69 lakh as interest for late possession
05 Jul 2021
2 Min Read
CW Team
The National Consumer Disputes Redressal Commission has ordered Runwal 亚博体育官网首页s to hand over a 1,215 sq ft Nahur flat to a Kemp鈥檚 Corner family and pay Rs 69 lakh interest, on the amount paid so far.
The commission informed that the builder might adjust the interest amount against the family鈥檚 balance payment for the flat.
The opposite party (builder) had to complete the construction and obtain the completion certificate and hand over possession to the flat allottee till March 2016. From the added evidence, it is confirmed that the Building Completion Certificate was issued on July 17, 2019.
The commission said that there is no proof or allegation filed to show that due to force majeure or the reasons specified in the contract, the construction could not be executed within the agreed time.
After the complainants, Arun Kedia and his family, who had already paid Rs 2.3 cr of the total amount of Rs 2.5 cr until August 2015, did not want to pay further until the builder assured possession after the March 2016 deadline terminated, the builder had cancelled the agreement. The commission said that due to lapses on the part of the opposite party (builder), the complainants are bearing a loss. The agreement for sale has been revoked illegally and is mala fide.
The commission said that the agreement claimed that the flat buyers should be given 30 days鈥� notice in writing before cancelling the agreement. There was no such notice issued. The intimation of cancellation was given through a letter dated March 15, 2017, which was illegal. The complaint was filed in 2017. The agreement date was June 5, 2013, and the possession was to be handed over by March 2016.
Also read: UP RERA has decided to organise National Lok Adalat on July 10
Also read: Model Tenancy Act to make an effective rental market place in India
The National Consumer Disputes Redressal Commission has ordered Runwal 亚博体育官网首页s to hand over a 1,215 sq ft Nahur flat to a Kemp鈥檚 Corner family and pay Rs 69 lakh interest, on the amount paid so far.
The commission informed that the builder might adjust the interest amount against the family鈥檚 balance payment for the flat.
The opposite party (builder) had to complete the construction and obtain the completion certificate and hand over possession to the flat allottee till March 2016. From the added evidence, it is confirmed that the Building Completion Certificate was issued on July 17, 2019.
The commission said that there is no proof or allegation filed to show that due to force majeure or the reasons specified in the contract, the construction could not be executed within the agreed time.
After the complainants, Arun Kedia and his family, who had already paid Rs 2.3 cr of the total amount of Rs 2.5 cr until August 2015, did not want to pay further until the builder assured possession after the March 2016 deadline terminated, the builder had cancelled the agreement. The commission said that due to lapses on the part of the opposite party (builder), the complainants are bearing a loss. The agreement for sale has been revoked illegally and is mala fide.
The commission said that the agreement claimed that the flat buyers should be given 30 days鈥� notice in writing before cancelling the agreement. There was no such notice issued. The intimation of cancellation was given through a letter dated March 15, 2017, which was illegal. The complaint was filed in 2017. The agreement date was June 5, 2013, and the possession was to be handed over by March 2016.
Image Source
Also read: UP RERA has decided to organise National Lok Adalat on July 10
Also read: Model Tenancy Act to make an effective rental market place in India
Next Story
Kolkata鈥檚 luxury housing market sees price growth amid mixed trends
A new study by Nklusive reveals that Kolkata鈥檚 luxury residential market (Rs 5鈥�10 crore) recorded a 33 per cent year-on-year rise in supply and a 52 per cent increase in sales in calendar year 2024 (CY24). South Kolkata led with 78 per cent of the segment鈥檚 supply. The average price rose by 6 per cent鈥攆rom Rs 17,519 to Rs 18,600 per sq ft鈥攚hile unsold inventory grew by 15 per cent. Monthly absorption improved from 2 to 3 units.In contrast, the ultra-luxury segment (Rs 10 crore and above) experienced a 17 per cent decline in supply and a 30 per cent fall in sales. Central Kolkata acco..
Next Story
New Expressway to Cut Pune-Bengaluru Travel Time by Half
The upcoming Pune-Bengaluru Expressway is expected to significantly improve connectivity and economic opportunities across Maharashtra and Karnataka. This 700-kilometre greenfield, access-controlled highway will cut the travel time between Pune and Bengaluru from 15 hours to just 7 hours, facilitating easier movement for both commuters and businesses. Starting from Bommanal in Karnataka鈥檚 Athani Taluk, the expressway will traverse important districts such as Belagavi, Bagalkot, and Jamakhandi. It will then enter Maharashtra at Kanjle, connect with the proposed Pune Ring Road, and pass throug..
Next Story
Nagpur鈥檚 Koradi Naka to Get Y-Shaped Flyover for Safer, Smoother Traffic
To alleviate traffic congestion and enhance safety at Koradi Naka in Nagpur, a Y-shaped flyover is currently being constructed on National Highway 47. Demolition work has already commenced, with the main construction scheduled to start on June 20, 2025.The project, costing Rs 430.37 billion, involves building a 1,090-meter-long flyover that will connect Farsa, the Mahadula Railway Overbridge (ROB), and Bokhara Road, and will also feature an underpass. The existing structure will be repurposed into a service road to facilitate local traffic.Koradi Naka has been identified as a significant "blac..